Northwire Canada EditionSaturday, July 18, 2026
Northwire
AII 19.25 +3.9% GGA 5.95 +12.3% VM 0.140 +3.7% GSR 0.365 +1.4% QCX 0.195 +0.0% EAU 0.085 +0.0% MCM 0.310 +0.0% BAT 0.100 +5.3% SFR 0.370 +68.2% FFU 0.125 +4.2% TVI 0.045 −10.0% ZNX 0.080 +0.0% TSK 1.06 +0.9% OMM 0.050 +0.0% EMO 0.320 −7.2% MDM 0.060 +0.0% AII 19.25 +3.9% GGA 5.95 +12.3% VM 0.140 +3.7% GSR 0.365 +1.4% QCX 0.195 +0.0% EAU 0.085 +0.0% MCM 0.310 +0.0% BAT 0.100 +5.3% SFR 0.370 +68.2% FFU 0.125 +4.2% TVI 0.045 −10.0% ZNX 0.080 +0.0% TSK 1.06 +0.9% OMM 0.050 +0.0% EMO 0.320 −7.2% MDM 0.060 +0.0%
Technical Study

Integra Resources files FS technical report for DeLamar

ITR · Price

Executive Summary

  • Integra Resources Corp. has filed a National Instrument 43-101 compliant Feasibility Study (FS) technical report for its wholly owned DeLamar gold and silver heap leach project in southwestern Idaho.
  • The FS confirms robust economics for a low-cost, large-scale, conventional open-pit oxide heap leach operation, projecting 1.1 million ounces of gold equivalent (AuEq) over a 10-year mine life plus two years of residual leaching.
  • The project demonstrates strong financial metrics, including an after-tax NPV of $774 million (at 5% discount rate) and an IRR of 46% at base-case metal prices, with significant upside to $1.9 billion NPV and 97% IRR at recent higher metal prices.

Key Details

  • Project Location: DeLamar and Florida Mountain deposits, Owyhee County, southwestern Idaho.
  • Production Profile:
    • Total production: 1.1 million ounces AuEq.
    • Mine Life: 10 years of operation plus two years of residual leaching.
    • Average Annual Production: 106,000 ounces AuEq per annum.
  • Cost Structure:
    • Co-product mine site All-In Sustaining Cost (AISC): $1,480 per ounce AuEq.
  • Financial Metrics (Base Case):
    • Metal Prices: $3,000/oz Gold, $35/oz Silver.
    • After-tax NPV (5%): ~$774 million.
    • After-tax IRR: 46%.
  • Financial Metrics (Recent Prices Scenario):
    • Metal Prices: $4,500/oz Gold, $65/oz Silver.
    • After-tax NPV (5%): ~$1.9 billion.
    • After-tax IRR: 97%.
  • Technical Report Details:
    • Title: "Feasibility Study and Technical Report on the DeLamar Project, Owyhee County, Idaho, USA."
    • Effective Date: December 8, 2025.
    • Lead Author/Consultant: Forte Dynamics Inc.
    • Filing Platforms: SEDAR+ and EDGAR.
  • Qualified Person: James Frost, PEng, Director, Technical Services, Integra Resources Corp.

Notable Quotes

  • No direct quotes from the CEO or President were included in the provided text.
Read the original news release →

More from Integra Resources Corp.