Gold 3,886.30 +0.0% Silver 49.12 −1.9% Copper 6.09 −1.7% Oil 88.56 −0.2% Palladium 1,007.60 +1.6% PPTA 25.29 −0.6% AIR 0.050 −9.1% PMX 0.055 +0.0% CCMC 0.340 +0.0% PPM 0.095 +0.0% BMR 0.165 +0.0% S 0.175 +0.0% STGO 1.37 −2.8% GRDM 0.180 +0.0% CRI 0.015 +0.0% CN 0.120 +0.0% BTT 0.100 −13.0% AUXX 5.07 −2.9% CLV 0.120 + VUL 0.360 −5.3% LUNR 15.66 −3.1% Gold 3,886.30 +0.0% Silver 49.12 −1.9% Copper 6.09 −1.7% Oil 88.56 −0.2% Palladium 1,007.60 +1.6% PPTA 25.29 −0.6% AIR 0.050 −9.1% PMX 0.055 +0.0% CCMC 0.340 +0.0% PPM 0.095 +0.0% BMR 0.165 +0.0% S 0.175 +0.0% STGO 1.37 −2.8% GRDM 0.180 +0.0% CRI 0.015 +0.0% CN 0.120 +0.0% BTT 0.100 −13.0% AUXX 5.07 −2.9% CLV 0.120 + VUL 0.360 −5.3% LUNR 15.66 −3.1%
M&A / Property

Midland signs deal with Barrick for Lewis gold property

MD · Price

Executive Summary

  • Midland Exploration Inc. has signed a definitive option agreement with a wholly owned indirect subsidiary of Barrick Mining Corp. to acquire up to a 75% interest in the Lewis gold property in Quebec.
  • Barrick can earn an initial 51% interest by paying $250,000 in cash and completing $3 million in exploration work by December 31, 2028.
  • Barrick can further increase its stake to 60% and then 75% through additional cash payments and exploration spending milestones, totaling $750,000 in cash and $12 million in exploration work by December 31, 2032.

Key Details

  • Transaction Structure: Definitive option agreement for the Lewis gold property, currently 100% owned by Midland.
  • Counterparty: Barrick Mining Corp. (via a wholly owned indirect subsidiary).
  • Total Earn-In Potential: Barrick can acquire up to a 75% interest.
  • Total Consideration:
    • Cash: $750,000 total.
    • Exploration Work: $12,000,000 total.
  • Milestone 1 (51% Interest):
    • Deadline: On or prior to Dec. 31, 2028.
    • Cash Payment: $250,000.
    • Exploration Work: At least $3,000,000 (including a guaranteed $200,000).
    • Result: Formation of a Joint Venture (JV).
  • Milestone 2 (60% Interest):
    • Deadline: On or prior to Dec. 31, 2030.
    • Cash Payment: $200,000.
    • Exploration Work: At least $1,500,000.
  • Milestone 3 (75% Interest):
    • Deadline: On or prior to Dec. 31, 2032.
    • Cash Payment: $300,000.
    • Exploration Work: At least $7,500,000.
  • Dilution/NSR Clause: If Barrick fails to exercise funding options, JV interests are subject to proportionate funding and dilution terms. Dilution to or below a 10% JV interest converts the interest to a 2% Net Smelter Return (NSR) royalty, with the right to repurchase 50% of the NSR (reducing it to 1%) for $1.5 million.
  • Operator: Barrick will be the operator of the exploration work.
  • Property Location: Approximately 60 km southwest of Chapais, Abitibi, Quebec.
  • Property Assets: 154 exclusive exploration rights (86 square kilometres).
  • Strategic Context:
    • Located ~60 km northwest of Iamgold’s Nelligan deposit (106.4M tonnes inferred @ 0.96 g/t Au; 102.8M tonnes indicated @ 0.85 g/t Au).
    • Located ~10 km west of the former Lac Shortt mine (historically produced 2.7M tonnes @ 4.6 g/t Au).