B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Production / Operations

Electra signs $6.1M (U.S.) refinery project contract

ELBM · Price

Executive Summary

  • Electra Battery Materials Corp. has awarded a $6.1 million (US) contract to EXP Services Inc. for engineering, project management, and construction management services for its Ontario cobalt sulphate refinery.
  • The company is advancing toward mechanical completion and commissioning in the first half of 2027, with production expected to follow shortly after.
  • The facility is currently in the final phase of construction, with key civil, mechanical, and structural work largely completed, including foundations and major equipment installation.

Key Details

  • Contract Award: $6.1 million (US) / $8.3 million (CAD) awarded to EXP Services Inc.
  • Scope of Work: Engineering, project management, and construction management services during the construction phase of the Ontario battery material refinery.
  • Project Status: Entering the final phase of construction; targeting mechanical completion in the first half of 2027.
  • Completed Work: Key civil, mechanical, and structural work completed, including foundations, utilities, the solvent extraction building, and much of the installation of key solvent extraction and crystallizer equipment.
  • Recent Activities:
    • Restarted procurement process for key piping and electrical components (automated valves and control systems).
    • Advanced site preparation, including laydown areas, warehousing, and logistics support.
    • Completed finalizing detailed engineering, piping and instrumentation diagrams, and Hazop reviews.
  • Production Targets:
    • Initial capacity: 5,100 tonnes of cobalt annually in battery-grade cobalt sulphate.
    • Future expansion: 6,500 tonnes of contained cobalt in sulphate per year.
  • Strategic Context: The refinery is North America's only cobalt sulphate refinery under development, located in Temiskaming Shores, Ontario.

Notable Quotes

  • "Partnering with EXP provides Electra with the additional project and construction management support needed as we move into the final phase of refinery development," said Paolo Toscano, vice-president, project and engineering.
  • "Electra is focused on commissioning its cobalt sulphate refinery in 2027... Electra's facility is positioned as a strategic asset to support North America's military and industrial base," said Trent Mell, chief executive officer.