Northwire Canada EditionSunday, July 19, 2026
Northwire
AII 19.25 +3.9% GGA 5.95 +12.3% VM 0.140 +3.7% GSR 0.365 +1.4% QCX 0.195 +0.0% EAU 0.085 +0.0% MCM 0.310 +0.0% BAT 0.100 +5.3% SFR 0.370 +68.2% FFU 0.125 +4.2% TVI 0.045 −10.0% ZNX 0.080 +0.0% TSK 1.06 +0.9% OMM 0.050 +0.0% EMO 0.320 −7.2% MDM 0.060 +0.0% AII 19.25 +3.9% GGA 5.95 +12.3% VM 0.140 +3.7% GSR 0.365 +1.4% QCX 0.195 +0.0% EAU 0.085 +0.0% MCM 0.310 +0.0% BAT 0.100 +5.3% SFR 0.370 +68.2% FFU 0.125 +4.2% TVI 0.045 −10.0% ZNX 0.080 +0.0% TSK 1.06 +0.9% OMM 0.050 +0.0% EMO 0.320 −7.2% MDM 0.060 +0.0%
M&A / Property

Tethys Petroleum Press Release: Corporate Update

TPL · Price

Executive Summary

  • Oil production averaging ~380 t/d is expected to rise to ~530 t/d after commissioning of a second gas compressor within a week.
  • New gas processing and pipeline projects are in design, with targeted commissioning dates of Oct 2026 (gas facility) and mid‑Jan 2026 (central processing upgrade).
  • The Special Committee continues discussions with Fincraft Group LLP regarding a non‑binding LOI to acquire Tethys; a response is pending.

Key Details

  • Current Oil Production: ~380 tons per day from wells KBD‑02, KBD‑06, KBD‑07 (last month).
  • Second Gas Turbine Repair: Completed; expected to boost oil‑to‑gas utilization capacity to ~480 t/d immediately.
  • Second Gas Compressor Pre‑Commissioning: Ongoing; anticipated increase to ~530 t/d after start‑up within a week.
  • Central Processing Facility Upgrade (Kul‑Bas Oil Field): Underway; commissioning scheduled for mid‑January 2026.
  • Gas Processing Facility & 6" × 18 km Pipeline Project: At design stage; targeted operational date October 2026.
  • Natural Gas Production: ~222,000 m³/day from 21 wells in Kyzyloi and Akkulka fields. Ongoing workover to reactivate suspended wells.
  • Exploration Activities: Evaluation of Aral‑4 prospect ongoing; permitting & preparatory work for drilling at two priority sites; seismic interpretation for Diyar block progressing; vintage 2D seismic analysis for northern Diyar, southern Zhanasu and Nurzhau blocks continuing.
  • Regulatory Submission (Nov 27 2025): Application to transition Contract No. 1897 for Kul‑Bas field to Production Period (Commercial License) submitted to Kazakhstan Ministry of Energy; statutory review period 20 working days.
  • Potential Acquisition: Special Committee sent a letter to Fincraft Group LLP on Nov 26 2025 regarding their intent to acquire Tethys; awaiting response.

Notable Quotes

(No direct quotes were provided in the release.)

Read the original news release →

More from Tethys Petroleum Limited