GOLD 4107.90 −1.7% SILVER 55.88 −6.1% COPPER 6.62 −1.6% OIL 95.09 +1.0% PALLADIUM 1096.50 −2.7% CIA 2.64 −0.4% BTO 7.09 −4.3% MCI 0.155 +0.0% CAN 0.065 +0.0% BLDS 0.335 +8.1% SAO 0.050 +0.0% SF 0.315 +0.0% BEA 0.055 −15.4% BMM 3.90 +11.1% AUGC 0.295 −13.2% MFG 3.34 −3.8% CDE 21.33 −7.7% CYG 0.160 −5.9% RSMX 0.100 −4.8% TUF 0.830 −5.7% GPG 0.285 −3.4% GOLD 4107.90 −1.7% SILVER 55.88 −6.1% COPPER 6.62 −1.6% OIL 95.09 +1.0% PALLADIUM 1096.50 −2.7% CIA 2.64 −0.4% BTO 7.09 −4.3% MCI 0.155 +0.0% CAN 0.065 +0.0% BLDS 0.335 +8.1% SAO 0.050 +0.0% SF 0.315 +0.0% BEA 0.055 −15.4% BMM 3.90 +11.1% AUGC 0.295 −13.2% MFG 3.34 −3.8% CDE 21.33 −7.7% CYG 0.160 −5.9% RSMX 0.100 −4.8% TUF 0.830 −5.7% GPG 0.285 −3.4%
Production / Operations

Tethys Petroleum Press Release

TPL · Price

Executive Summary

  • Oil production from wells KBD‑02, KBD‑06 and KBD‑07 averaged ~323 t/d in early 2026 and rebounded to 375 t/d after weather‑related disruptions.
  • Natural gas output from the Kyzyloi and Akkulka fields is averaging about 222,000 m³/day across 20 wells.
  • Drilling of ARD#1 (Kronos) in the Aral 4 block is slated to start early May 2026, with KBD‑5 planned for early August 2026.

Key Details

  • Oil Production:
  • Average 323 tons per day (2026 to date).
  • After weather‑related shutdowns, production increased to 375 tons per day as of the latest report.
  • Gas Production:
  • Current average 222,000 m³ per day from 20 gas wells in the Kyzyloi and Akkulka fields.
  • Regulatory Approvals:
  • Gas utilization program for Kul Bas approved through end‑2026 by Ministry of Energy working group (Mar 12).
  • Expert panel approved extension of the Akkulka Gas Contract and removed reinvestment obligation on incremental oil product price gains.
  • Facility Upgrades:
  • Central processing facility upgrade and storage capacity expansion is ~80% complete for the current construction phase.
  • Drilling Schedule:
  • ARD#1 (Kronos) – Aral 4 block, planned start early May 2026; target depth ≈3,000 m (+250 m).
  • KBD‑5 – scheduled to commence early August 2026; target depth ≈2,500 m (±250 m).

Notable Quotes

No executive quotes were included in the release.

Read the original news release →