Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5% Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5%
Production / Operations

Tethys Petroleum Press Release

TPL · Price

Executive Summary

  • Oil production from wells KBD‑02, KBD‑06 and KBD‑07 averaged ~323 t/d in early 2026 and rebounded to 375 t/d after weather‑related disruptions.
  • Natural gas output from the Kyzyloi and Akkulka fields is averaging about 222,000 m³/day across 20 wells.
  • Drilling of ARD#1 (Kronos) in the Aral 4 block is slated to start early May 2026, with KBD‑5 planned for early August 2026.

Key Details

  • Oil Production:
  • Average 323 tons per day (2026 to date).
  • After weather‑related shutdowns, production increased to 375 tons per day as of the latest report.
  • Gas Production:
  • Current average 222,000 m³ per day from 20 gas wells in the Kyzyloi and Akkulka fields.
  • Regulatory Approvals:
  • Gas utilization program for Kul Bas approved through end‑2026 by Ministry of Energy working group (Mar 12).
  • Expert panel approved extension of the Akkulka Gas Contract and removed reinvestment obligation on incremental oil product price gains.
  • Facility Upgrades:
  • Central processing facility upgrade and storage capacity expansion is ~80% complete for the current construction phase.
  • Drilling Schedule:
  • ARD#1 (Kronos) – Aral 4 block, planned start early May 2026; target depth ≈3,000 m (+250 m).
  • KBD‑5 – scheduled to commence early August 2026; target depth ≈2,500 m (±250 m).

Notable Quotes

No executive quotes were included in the release.