MEK 0.055 +0.0% TGOL 0.100 −9.1% FCI 0.400 −7.0% SGQ 0.350 +0.0% SASK 0.980 −3.9% WGX 4.60 −1.5% GMX 1.88 +2.7% DSV 8.80 −3.5% MQM 0.170 +0.0% MNO 1.52 −2.6% VIZ 0.190 +0.0% HBM 31.87 +0.1% CNC 1.52 −3.8% ALGR 0.490 −7.5% MSG 0.200 −2.4% ECU 1.72 +1.8% MEK 0.055 +0.0% TGOL 0.100 −9.1% FCI 0.400 −7.0% SGQ 0.350 +0.0% SASK 0.980 −3.9% WGX 4.60 −1.5% GMX 1.88 +2.7% DSV 8.80 −3.5% MQM 0.170 +0.0% MNO 1.52 −2.6% VIZ 0.190 +0.0% HBM 31.87 +0.1% CNC 1.52 −3.8% ALGR 0.490 −7.5% MSG 0.200 −2.4% ECU 1.72 +1.8%
Technical Study

Great Pacific to file updated Kesar NI 43-101 report

GPAC · Price

Executive Summary

  • Great Pacific Gold Corp. is filing an updated NI 43-101 technical report for its Kesar Gold Project in Papua New Guinea, highlighting results from a Phase 1 exploration program completed in May 2025.
  • The Phase 1 program consisted of 13 diamond drill holes totaling 3,714.3 meters, identifying multiple high-grade gold intercepts at the Anteruno and Hampore targets.
  • The report recommends a Phase 2 exploration program for 2026, including surface exploration, ground truthing of mobile MT geophysics targets, and a 3,000-meter diamond drill program.

Key Details

  • Drilling Results (Phase 1):
    • Total scope: 13 holes, 3,714.3 meters of diamond drilling.
    • Anteruno Target: Best intercept of 3.13 meters at 3.67 grams per tonne gold (g/t Au), including 0.71 meters at 13.5 g/t Au (Hole KDH003).
    • Hampore Target: Best intercept of 0.94 meters at 3.17 g/t Au, including 0.29 meters at 9.08 g/t Au (Hole KDH011).
    • Mineralization interpreted as narrow-to-very-narrow quartz veins carrying significantly high gold grades (>10 g/t Au) within phyllic alteration haloes.
  • Geophysics:
    • Completed an airborne mobile magnetotelluric (MT) survey covering 931 line kilometers over 143 square kilometers.
    • Lineament analysis identified multiple high-potential targets for both porphyry-style mineralization and intermediate-sulphidation epithermal deposits.
  • Future Plans (Phase 2):
    • Recommended for 2026 following the renewal of the exploration license (EL 2711).
    • Includes surface exploration, ground truthing of MT targets, target/drill-scale mapping, sampling, trenching, and a 3,000-meter diamond drill program.
  • Project Economics & History:
    • Total expenditures on Kesar during the initial two-year license period (Oct 30, 2023 – Oct 30, 2025) were approximately $5.8 million (16.7 million Papua New Guinean kina).
    • Great Pacific Gold holds a 90% interest in Yaendal Minerals Ltd., which holds the license, with an option to acquire the remaining 10% upon completion of a definitive feasibility study.
    • The project is located immediately adjacent to K92 Mining’s Kainantu mine.
  • Technical Report Details:
    • Prepared by H&S Consultants Pty. Ltd.
    • Effective date: September 9, 2025.
    • Qualified Person: Callum Spink, VP Exploration.

Notable Quotes

  • "While Wild Dog remains our top priority target, Kesar has tremendous potential and is strategically located alongside K92 Mining's Kainantu mine... We are planning a focused follow-up program at Kesar with the objective of unlocking value that we believe is currently not recognized in our share price." — Greg McCunn, CEO
  • "With over 16.7 million Papua New Guinean kina ($5.8-million) spent on Kesar over the initial two-year licence period, GPAC is one of the largest active exploration companies in Papua New Guinea." — Greg McCunn, CEO