Electra Battery talks work on cobalt sulphate refinery

ELBM · Price
Executive Summary
- Electra Battery Materials Corp. provided a construction progress update on its cobalt sulfate refinery in Ontario, confirming that procurement and installation are on track with the $73-million budget and mechanical completion is targeted for Q2 2027.
- The company received a Nasdaq notice of non-compliance with the $1 minimum bid price requirement, granting a 180-day cure period until September 14, 2026, to regain compliance.
- Significant engineering and infrastructure milestones were achieved, including the completion of fire suppression and P&ID designs, installation of effluent tanks, and awarding of $1.9 million in key process system purchase orders.
Key Details
- Project Timeline & Budget:
- Construction budget approved by the board: $73 million (U.S.).
- Mechanical completion target: Second quarter of 2027.
- Commissioning activities: Beginning late 2026.
- Production ramp-up: Expected in 2027.
- Engineering & Design Milestones:
- Fire suppression system design completed.
- Piping and Instrumentation Diagrams (P&ID) finalized and being integrated into the 3-D plant model.
- Comprehensive tailings area test work program completed (test pits, boreholes, lab testing); data delivered to engineering for detailed design.
- Construction & Installation Progress:
- Solvent Extraction (SX) Building: Survey and layout for anchor bolt placement for the pregnant leach solution (PLS) filter platform completed; raffinate tanks positioned, grouted, and anchored.
- Infrastructure: Installation of several effluent tanks completed; structural pipe racks connecting major process buildings installed; clarifier tank installations completed; site power infrastructure and construction support facilities upgraded.
- Procurement:
- Purchase orders awarded for key process systems, including:
- Plant control system
- Bag breaker system
- Neutralization clarifier
- SX strip solution filter
- PLS filter platform
- Total value of these specific awards: Approximately $1.9 million.
- Majority of major mechanical and electrical equipment already secured and delivered to site.
- Purchase orders awarded for key process systems, including:
- Nasdaq Compliance Notice:
- Date of Notice: March 16, 2026.
- Reason: Non-compliance with Nasdaq Listing Rule 5550(a)(2) (minimum bid price of $1.00 USD per share) based on 30 consecutive business days of closing bids below $1.00.
- Cure Period: 180 calendar days from the notice date, expiring on September 14, 2026.
- Compliance Mechanism: Company can regain compliance by closing at or above $1.00 for a minimum of 10 consecutive business days.
- Extension: If compliance is not met by Sept 14, 2026, the company may be eligible for an additional 180-day period upon satisfying certain listing requirements.
- Impact: No immediate effect on listing or trading; operations unaffected; no impact on TSX Venture Exchange listing.
Notable Quotes
- "Steady progress continues at the North American refinery project site," said Paolo Toscano, vice-president, projects and engineering. "With early works now largely complete, including key infrastructure installations and engineering milestones, the project is well positioned to transition into its next phase of construction."