VZZ 0.180 +2.9% BMR 0.145 +3.6% NVO 0.055 −8.3% PMET 4.47 +2.0% CTG 0.125 +13.6% AVU 0.040 +0.0% SGML 14.32 −3.1% WRLG 0.720 +1.4% CAN 0.065 +8.3% ABRA 15.63 +1.6% LSTR 0.060 +0.0% OLA 13.10 +2.5% EQX 13.15 +2.7% SRA 0.780 +0.0% UTWO 0.390 −13.3% IVN 10.64 −1.2% VZZ 0.180 +2.9% BMR 0.145 +3.6% NVO 0.055 −8.3% PMET 4.47 +2.0% CTG 0.125 +13.6% AVU 0.040 +0.0% SGML 14.32 −3.1% WRLG 0.720 +1.4% CAN 0.065 +8.3% ABRA 15.63 +1.6% LSTR 0.060 +0.0% OLA 13.10 +2.5% EQX 13.15 +2.7% SRA 0.780 +0.0% UTWO 0.390 −13.3% IVN 10.64 −1.2%
Regulatory

Canacol Energy Ltd Provides Information on Arbitration Process

CNE · Price

Executive Summary

  • Canacol Energy was notified that a domestic arbitration tribunal has ruled it must pay approximately USD 22 million to VP Ingenergía S.A.S. E.S.P., with the award becoming binding on November 20, 2025.
  • The company is reviewing the decision alongside outstanding invoices from VP Ingenergía (≈ USD 25 million) and will consider appeals or other legal actions.
  • Canacol continues its international arbitration claim against VP Ingenergía for > USD 76 million and expects a favorable outcome by the first half of 2026, while also pursuing criminal proceedings against VP Ingnergía’s directors and shareholders.

Key Details

  • The domestic arbitration addressed termination of three natural‑gas supply contracts that Canacol ended due to VP Ingenergía’s breach (failure to provide required guarantees and non‑payment for gas delivered).
  • The tribunal accepted Canacol’s arguments on the invalidity of the guarantees and irregular handling of proceeds, but partially upheld VP Ingnergía’s force‑majeure claims, resulting in a USD 22 million payment obligation for Canacol.
  • The award is not yet final; it will become binding after clarification/supplementation by November 20, 2025.
  • Canacol notes that VP Ingenergía still owes approximately USD 25 million in unpaid invoices and has court‑issued payment orders in its favor.
  • An international arbitration proceeding is underway where Canacol seeks > USD 76 million from VP Ingenergía; the domestic decision supports Canacol’s position, and a positive resolution is anticipated in H1 2026.
  • The company will submit the domestic arbitral decision to Colombia’s Attorney General’s Office, linking it to criminal charges (aggravated fraud, corruption) against VP Ingnergía’s owners/directors: Álvaro Augusto Vargas Bravo, Patricia Peña, and Darlyn Yesenia Neira, including requests for preventive detention.
  • Canacol is reviewing the full arbitral decision and will analyze potential appeals or further legal actions as appropriate.