AVX 0.005 −nan% AII 19.91 −1.0% GWM 0.480 +0.0% GEN 0.065 +0.0% NIO 0.135 −3.6% III 7.22 −2.8% NCAU 0.295 −3.3% NEV 0.040 +0.0% ITR 3.00 −1.6% ALDE 2.79 −0.7% TECK 84.18 +4.4% FVI 11.83 −2.2% SUM 1.31 −1.5% RSMX 0.115 +4.5% STW 0.105 +5.0% PAT 0.250 +0.0% AVX 0.005 −nan% AII 19.91 −1.0% GWM 0.480 +0.0% GEN 0.065 +0.0% NIO 0.135 −3.6% III 7.22 −2.8% NCAU 0.295 −3.3% NEV 0.040 +0.0% ITR 3.00 −1.6% ALDE 2.79 −0.7% TECK 84.18 +4.4% FVI 11.83 −2.2% SUM 1.31 −1.5% RSMX 0.115 +4.5% STW 0.105 +5.0% PAT 0.250 +0.0%
Production / Operations

PowerBank Receives $1.47 Million USD from NYSERDA for Geddes Solar Project

SUNN · Price

Executive Summary

  • PowerBank Corporation received a Commercial Operation Payment of $1.47 million USD from NYSERDA for its 3.79 MW Geddes Solar Power Project in New York State.
  • The project also qualifies for an additional $245,000 USD under the Inclusive Community Solar Adder, bringing total anticipated incentive proceeds to ~$1.72 million USD.
  • The payment reflects successful qualification for multiple NY‑Sun program adders (Megawatt Block, Community Adder, Landfill/Brownfield Adder) and supports PowerBank’s pipeline of >1 GW of development capacity.

Key Details

  • Project: Geddes Solar Power Project – 3.79 MW operating community solar facility built on a closed landfill in New York State.
  • Incentive Received: $1.47 million USD (Commercial Operation Payment) from NYSERDA’s NY‑Sun Program.
  • Additional Incentives Expected: $245,000 USD under the Inclusive Community Solar Adder (ICSA).
  • Program Adders Qualified:
  • Megawatt Block
  • Community Adder
  • Landfill/Brownfield Adder
  • Power Output Impact: Sufficient energy to power approximately 450 homes annually.
  • Company Portfolio Context: PowerBank has completed >100 MW of projects and maintains a development pipeline exceeding 1 GW.

Notable Quotes

(No direct quotes were provided in the release.)