Drill Results
Selkirk Copper Reports Additional Intersections of High-Grade Cu-Au-Ag From the Phase 1 Drill Program at the Minto Copper-Gold-Silver Mine
Selkirk Copper Drill Program Completion Validates Minto Restart Path Amidst Capital Raise

Executive Summary
- The most recent release (April 30, 2026) confirms the completion of Phase 1 drilling at the Minto Mine with 52,288 metres drilled across 175 holes.
- Results highlight high-grade intersections including an 8.3% CuEq intercept in Area 118 and significant copper-gold-silver grades in Minto North and Ridgetop South.
- The program exceeded its initial target by 5%, completing 105% of the planned scope with low cost-per-metre productivity.
- A concurrent financing update (April 29, 2026) notes Selkirk First Nation exercised anti-dilution rights to invest C$500,250 at $1.15 per share.
- Previous news (April 15, 2026) announced the assumption of site operations from the Yukon Government and confirmed the drilling completion milestone.
- The April 9, 2026 financing raised approximately C$20 million via a bought-deal private placement to fund development and working capital.
Material Impact
- Confirmation of Milestones: The Phase 1 drill program completion is a critical prerequisite for the Preliminary Economic Assessment (PEA) scheduled for mid-2026. This news confirms the company is on track to deliver the data required for the restart decision targeted in early 2027.
- Grade Validation: While the high-grade results are positive, they align with the narrative established since December 2025 (e.g., Dec 1, Dec 22, Jan 22 releases). The stock price has already rallied significantly from $0.18 to over $1.40 in anticipation of these results, suggesting much of this information is priced in.
- Financing Context: The Selkirk First Nation participation reinforces the strategic partnership but represents a relatively small amount (C$500k) compared to the C$20M bought deal raised earlier in April. It does not materially alter the capital structure or dilution profile significantly beyond what was already disclosed.
- Risk Mitigation: The assumption of site operations from the Yukon Government reduces regulatory uncertainty regarding care and maintenance, but it also transfers operational liability to Selkirk Copper before a final restart decision is made.
SCMI · Price
Company Overview
- Company: Selkirk Copper Mines Inc. (formerly Venerable Ventures Ltd.).
- Flagship Project: Minto Copper-Gold-Silver Mine in central Yukon.
- Project Status: Restart phase; transitioning from care and maintenance to development.
- Infrastructure: Existing 4,100 t/d mill, open-pit/underground mine infrastructure, power line, water treatment plant, and road/barge access valued at >C$300M (legacy).
- Resource Base: Indicated resources of ~12.6 Mt @ 1.2% Cu; Inferred resources of ~23.7 Mt @ 1.05% Cu.
- Timeline: PEA mid-2026, Feasibility Study mid-2027, Construction decision H2 2027, First production mid-2028.