Northwire Canada EditionWednesday, August 19, 2026
Northwire
ALS 62.72 +2.0% COS 0.060 −7.7% STRM 0.440 +1.1% SRC 1.73 −0.6% BAG 0.205 +0.0% ANK 0.340 −2.9% VRB 0.085 +0.0% CPAU 0.140 +0.0% RES 0.025 +0.0% TKO 11.85 +2.2% DCOP 0.075 +7.1% HMR 0.475 −3.1% LITH 0.425 −3.4% MKA 0.750 −2.6% NGC 0.100 −16.7% JUGR 1.38 +7.0% ALS 62.72 +2.0% COS 0.060 −7.7% STRM 0.440 +1.1% SRC 1.73 −0.6% BAG 0.205 +0.0% ANK 0.340 −2.9% VRB 0.085 +0.0% CPAU 0.140 +0.0% RES 0.025 +0.0% TKO 11.85 +2.2% DCOP 0.075 +7.1% HMR 0.475 −3.1% LITH 0.425 −3.4% MKA 0.750 −2.6% NGC 0.100 −16.7% JUGR 1.38 +7.0%
Technical Study

Amex Exploration Perron Gold Project Delivers Strong Economics in Updated PEA

AMX · Price

Executive Summary

  • Amex Exploration released an updated PEA for the wholly‑owned Perron gold project, incorporating the May 21 2025 Mineral Resource Estimate and a two‑stage production plan (4‑year toll‑milling phase followed by a 13‑year owner‑operated mine).
  • The base‑case model (US$2,500/oz Au, CAD 1.38/USD) shows an after‑tax NPV of C$1.085 billion, an after‑tax IRR of 70.1 %, and a payback period of 1.4 years; cumulative post‑tax free cash flow over 17.5 years is C$1.768 billion.
  • Initial net CAPEX is C$77.5 million (gross C$146.1 M offset by pre‑production gold sales of C$68.6 M); growth CAPEX for Phase 2 is C$191.6 M, with sustaining CAPEX of C$386.3 M.

Key Details

  • Project Scope & Timeline
  • Phase 1: 4‑year, 1,000 tpd contract mining/toll‑milling; net initial CAPEX C$77.5 M; average production 102,000 oz/yr at AISC US$1,165/oz.
  • Phase 2: 13‑year, 2,000 tpd owner‑operated mine with on‑site processing; growth CAPEX C$191.6 M; average production 93,000 oz/yr at AISC US$1,027/oz.
  • Total LOM 17.5 years; average annual gold output 95,000 oz (112,000 oz/yr for first 10 years).

  • Economic Highlights (Base Case)

  • After‑tax NPV (5% discount): C$1,085 M
  • After‑tax IRR: 70.1 %
  • Payback period: 1.4 years from commercial production start (target 2028).
  • Pre‑tax NPV: C$1,885 M; Pre‑tax IRR: 99.1 %.

  • Capital Structure

  • Initial CAPEX (gross): C$146.1 M → net after pre‑production offset: C$77.5 M.
  • Growth CAPEX (Phase 2): C$191.6 M.
  • Sustaining CAPEX (LOM): C$386.3 M.
  • Total projected capital outlay (gross): C$724.0 M; net cash‑required: C$655.4 M.

  • Operating Cost Summary

  • LOM average operating cost: US$891/oz Au.
  • LOM AISC: US$1,061/oz Au (placing the project in the bottom quartile of global gold cost curve).

  • Sensitivity Analyses

  • Gold price ±40 % changes NPV from C$500 M to C$1,924 M; IRR varies 20.7 %–111.5 %.
  • Operating‑cost variations (±40 %) shift NPV between C$811 M and C$1,354 M; IRR 56.1 %–82.8 %.
  • CAPEX ±40 % changes NPV from C$966 M to C$1,201 M; IRR 51.8 %–102.1 %.

  • Production & Recovery

  • Expected gold recovery for both toll‑milling and on‑site processing: ≈95 %.
  • Phase 1 toll‑mill cost assumption: C$102/tonne (sensitivity ±40 %).

  • Infrastructure & Workforce

  • Peak staffing: ~272 employees (Phase 1) and ~335 (Phase 2).
  • Required infrastructure includes 25 kV power line, substation, road network, water‑management facilities, and on‑site processing plant.

  • Environmental & Permitting

  • Environmental impact assessment underway; tailings to be stored in mined‑out open pits, eliminating a conventional tailings facility.
  • Multiple provincial and federal permits will be required before construction.

  • Exploration Update

  • Recent acquisition of Perron West property expands land package to 197.5 km².
  • Ongoing surface exploration and 3‑D lithostructural modelling to support a maiden drill program on Perron West in 2026.

  • Qualified Persons & Disclosures

  • Technical information signed off by a team of qualified engineers and geologists (Evomine, Bumigeme, P&E Mining Consultants, Norda Stelo, Laurentia Exploration).
  • Standard non‑GAAP financial measure disclosures included.

Notable Quotes

  • “Our staged approach to production and construction is both fiscally and technically prudent, minimizing permitting and technical risk, reducing upfront capital and enabling early cash flow.” – Victor Cantore, President & CEO.

Materiality Assessment: Material – Positive (the PEA provides a materially positive economic outlook for the Perron project, with high IRR/NPV metrics and detailed capital and operating cost structures).

Read the original news release →

More from Amex Exploration Inc.