Gold 4,030.20 −2.0% Silver 51.23 −2.8% Copper 6.23 −1.7% Oil 86.04 −0.9% Palladium 1,020.80 −0.1% ALS 53.01 −2.2% APM 5.13 −6.6% AVL 5.46 −5.4% NG 8.84 −9.0% ATY 0.220 −2.2% CN 0.125 −10.7% PMET 3.22 −4.2% ITH 1.99 −11.6% VMET 12.33 −6.9% ABX 56.41 −5.6% PUR 0.370 +8.8% SCY 0.085 +6.2% AUMN 0.300 +7.1% SLG 6.24 −0.9% MSC 0.020 +0.0% MCI 0.140 +0.0% Gold 4,030.20 −2.0% Silver 51.23 −2.8% Copper 6.23 −1.7% Oil 86.04 −0.9% Palladium 1,020.80 −0.1% ALS 53.01 −2.2% APM 5.13 −6.6% AVL 5.46 −5.4% NG 8.84 −9.0% ATY 0.220 −2.2% CN 0.125 −10.7% PMET 3.22 −4.2% ITH 1.99 −11.6% VMET 12.33 −6.9% ABX 56.41 −5.6% PUR 0.370 +8.8% SCY 0.085 +6.2% AUMN 0.300 +7.1% SLG 6.24 −0.9% MSC 0.020 +0.0% MCI 0.140 +0.0%
Technical Study

Gunnison Copper Announces Updated Preliminary Economic Assessment of Its Flagship Gunnison Copper Project Reporting Post-Tax NPV8 of US$2.0 Billion

GCU · Price

Executive Summary

  • Gunnison Copper Corp. released an updated NI 43‑101 PEA for its 100% owned Gunnison Copper Project, showing a post‑tax NPV₈ of US$1.95 billion and an IRR of 22.7%, representing a +55% ($692 M) increase versus the 2024 PEA.
  • The project now includes the high‑grade Strong & Harris satellite deposit (25 Mt @ 0.85% Cu), material sorting technology, cement/limestone co‑products, and other cost‑saving initiatives that together contribute ~83% of the NPV uplift.
  • Average annual copper cathode production is projected at 174 M lb (87 kt) for the first 15 years, with a life‑of‑mine of 21 years, cash costs of $1.69/lb Cu, and all‑in sustaining cost of $2.06/lb Cu.

Key Details

  • Project Scope & Scale
  • Open‑pit, heap‑leach, SX/EW operation producing 99.999% pure copper cathode.
  • Leach pad: 541 Mt @ 0.43% Cu (including 25 Mt @ 0.85% from Strong & Harris).
  • Total copper produced over LOM: 3.2 B lb; average annual production 174 M lb (first 15 yr).
  • Economic Highlights (Base Case $4.60/lb Cu)
  • NPV₈ (after‑tax): $1,952 M (vs. $1,260 M in 2024 PEA).
  • IRR (after‑tax): 22.7% (vs. 19.5% prior).
  • Payback period: 3.9 yr (vs. 5.2 yr prior).
  • Avg. annual free cash flow (Y1‑Y15): $366 M ($514 M at $5.75/lb spot).
  • Cost Structure
  • Cash cost (C₁): $1.69/lb Cu.
  • Sustaining cash cost: $2.00/lb Cu.
  • All‑in sustaining cost (AISC): $2.06/lb Cu – in lower half of global copper cost curve.
  • Capital Expenditures
  • Initial capex (incl. contingency): $1,544 M (excluding acid plant).
  • Expansion capex (cement plant, etc.): $682 M.
  • Sustaining capex: $613 M.
  • Major cost items: ore sorting equipment ($205.4 M), cement plant ($326 M), autonomous haul trucks ($14 M), acid plant reduction ($19 M).
  • Cement & Limestone Co‑products
  • Cement plant (1 Mt/yr) – capex $326 M, sales price $157.21/ton.
  • High‑purity limestone (133 Mt total) – sales $4.80/ton; adds $130 M NPV₈.
  • Resource Estimates (Effective 2026‑01‑23)
  • Gunnison Deposit: Measured 191.5 Mt @ 0.37% Cu, Indicated 654.5 Mt @ 0.31% Cu → 5,190 kt Cu contained.
  • Strong & Harris Deposit (satellite): Inferred 76 Mt @ 0.49% Cu, plus Zn/Ag credits.
  • Financial Model Inputs
  • Copper price assumption: $4.60/lb (consensus) / $5.75/lb (spot).
  • Acid price $210/ton (purchase), $190/ton (sale); sulfur $160/ton; diesel $2.96/gal; power $0.079/kWh.
  • Royalties & Metal Stream
  • Greenstone royalty: 3.0% gross revenue.
  • Triple Flag metal‑stream: 25 M lbpa payable copper at 25% of LME settlement price; upfront deposit $65 M received.
  • Additional royalties: Callinan (1%), ASLD sliding net return (2–8%).
  • Option Agreements
  • Option to acquire 3,906.57 acres of land – initial payment $1 M, annual $250k, final purchase price up to $37 M depending on timing.
  • Risk & Opportunity Highlights
  • Slope stability, blasting cost, leach‑pad hydraulics, acid consumption, permitting, and ISR vs. open‑pit options discussed.
  • Opportunities: material sorting (reduces acid use), steeper pit walls, higher copper recoveries, in‑pit leaching, expanded cement/limestone markets.
  • Next Steps
  • Recommendation to proceed with a Prefeasibility Study (PFS) (~18 months).
  • PFS budget: total $29.7 M covering resource upgrade, metallurgy, geotechnical work, pit design, and infrastructure studies.
  • Anticipated subsequent steps: detailed engineering, permitting, financing, and potential construction of cement plant (years 4‑5) after initial capex payback.

Notable Quotes

  • Dr. Stephen Twyerould, CEO: “The updated PEA underscores the scale and compelling economics… delivering an after‑tax NPV₈ of approximately US$2.0 billion, a 23% IRR, and a 3.9‑year payback… positioning Gunnison as one of the most financially compelling copper development projects in the United States.”
Read the original news release →