Denison Announces Award of Construction Management Contract to Wood Canada for the Phoenix Uranium Mine

DML · Price
Executive Summary
- Denison Mines Corp. awarded Wood Canada Limited a 24‑month construction management contract for the Phoenix in‑situ recovery uranium mine at Wheeler River.
- The contract covers full processing plant construction management, site infrastructure installation, integrated project controls, procurement support and safety oversight.
- The award is presented as a key milestone that positions Denison to proceed with site preparation and a Final Investment Decision once federal permits are received.
Key Details
- Contract Award: Wood Canada Limited (“Wood”) selected as construction manager for the Phoenix ISR mine after a competitive tender process.
- Scope of Services:
- Construction management of the processing plant.
- Installation of site infrastructure.
- Integrated project controls, procurement support, on‑site safety oversight, reporting and performance management.
- Project Timeline: Estimated 24‑month construction period following contract execution.
- Strategic Importance: Provides continuity from engineering to execution; enables efficient delivery of the Wheeler River Project.
- Regulatory Context: Construction planning proceeds pending receipt of Federal Environmental Assessment approval and licence to prepare the site and construct a mine and mill (anticipated shortly).
- Joint Venture Structure: Denison holds 90 % operating interest in Wheeler River JV; Wood will work directly with Denison’s project team.
- Financial Position: CEO noted Denison’s “strong balance sheet” supporting readiness for a Final Investment Decision once permits are secured.
Notable Quotes
“The selection of Wood for construction management allows us to leverage our long‑standing relationship… We stand ready to make a Final Investment Decision and commence construction shortly after securing Federal approval.” – David Cates, President & CEO, Denison Mines Corp.
“Our priority is to enable a safe and seamless transition into execution… delivering Phoenix safely and successfully.” – John Day, President of Projects Western Hemisphere, Wood