Gold 4,030.20 −2.0% Silver 51.23 −2.8% Copper 6.27 −1.2% Oil 86.04 −0.9% Palladium 1,024.00 +0.2% NVX 0.910 +0.0% MSR 0.435 +0.0% ELE 22.85 −4.0% ALS 53.01 −2.2% APM 5.13 −6.6% AVL 5.46 −5.4% NG 8.84 −9.0% ATY 0.220 −2.2% CN 0.125 −10.7% PMET 3.22 −4.2% ITH 1.99 −11.6% VMET 12.33 −6.9% ABX 56.41 −5.6% PUR 0.370 +8.8% SCY 0.085 +6.2% AUMN 0.300 +7.1% Gold 4,030.20 −2.0% Silver 51.23 −2.8% Copper 6.27 −1.2% Oil 86.04 −0.9% Palladium 1,024.00 +0.2% NVX 0.910 +0.0% MSR 0.435 +0.0% ELE 22.85 −4.0% ALS 53.01 −2.2% APM 5.13 −6.6% AVL 5.46 −5.4% NG 8.84 −9.0% ATY 0.220 −2.2% CN 0.125 −10.7% PMET 3.22 −4.2% ITH 1.99 −11.6% VMET 12.33 −6.9% ABX 56.41 −5.6% PUR 0.370 +8.8% SCY 0.085 +6.2% AUMN 0.300 +7.1%
Production / Operations

Denison Announces Award of Construction Management Contract to Wood Canada for the Phoenix Uranium Mine

DML · Price

Executive Summary

  • Denison Mines Corp. awarded Wood Canada Limited a 24‑month construction management contract for the Phoenix in‑situ recovery uranium mine at Wheeler River.
  • The contract covers full processing plant construction management, site infrastructure installation, integrated project controls, procurement support and safety oversight.
  • The award is presented as a key milestone that positions Denison to proceed with site preparation and a Final Investment Decision once federal permits are received.

Key Details

  • Contract Award: Wood Canada Limited (“Wood”) selected as construction manager for the Phoenix ISR mine after a competitive tender process.
  • Scope of Services:
  • Construction management of the processing plant.
  • Installation of site infrastructure.
  • Integrated project controls, procurement support, on‑site safety oversight, reporting and performance management.
  • Project Timeline: Estimated 24‑month construction period following contract execution.
  • Strategic Importance: Provides continuity from engineering to execution; enables efficient delivery of the Wheeler River Project.
  • Regulatory Context: Construction planning proceeds pending receipt of Federal Environmental Assessment approval and licence to prepare the site and construct a mine and mill (anticipated shortly).
  • Joint Venture Structure: Denison holds 90 % operating interest in Wheeler River JV; Wood will work directly with Denison’s project team.
  • Financial Position: CEO noted Denison’s “strong balance sheet” supporting readiness for a Final Investment Decision once permits are secured.

Notable Quotes

“The selection of Wood for construction management allows us to leverage our long‑standing relationship… We stand ready to make a Final Investment Decision and commence construction shortly after securing Federal approval.” – David Cates, President & CEO, Denison Mines Corp.

“Our priority is to enable a safe and seamless transition into execution… delivering Phoenix safely and successfully.” – John Day, President of Projects Western Hemisphere, Wood

Read the original news release →