NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0%
Resource Estimate Routine +

Thor Explorations Ltd. Announces Filing of NI 43-101 Technical Report on the Douta Gold Project, Senegal

THX · Price

Executive Summary

  • Thor Explorations filed an NI 43‑101 technical report confirming the results of its January 2026 Pre‑Feasibility Study for the Douta Gold Project in Senegal.
  • The PFS shows a pre‑tax NPV₅% of US$908 million and IRR of 73 %, with strong early cash flow (411 koz gold in first four years at AISC US$1,493/oz) and an anticipated payback period of 11 months.
  • Updated Mineral Resource Estimate (MRE) defines a Probable Reserve of 36.6 Mt @ 1.03 g/t Au for 1.2 Moz Au, supporting the long‑life production profile of ~1 Moz gold over 12.6 years.

Key Details

  • Pre‑tax Project NPV₅%: US$908 million (100 % equity) at a gold price assumption of US$3,500/oz.
  • Pre‑tax IRR: 73 % (100 % equity).
  • Post‑tax Project NPV₅%: US$633 million; Post‑tax IRR: 61 %.
  • Early Cash Flow: 411 koz gold produced in the first four years (Oxide Ore Phase) at AISC US$1,493/oz, generating pre‑tax cash flow of US$814 million and net post‑repayment cash flow of US$561 million.
  • Payback Period: ~11 months from start of processing; improves to 9 months at spot gold price ≈US$4,250/oz.
  • Long‑life Production Profile: 1.0 Moz gold from 37 Mt mill feed (average grade 1.03 g/t Au) over 12.6 years; total contained metal 1.2 Moz.
  • Initial Capital Cost: US$254 million; Life‑of‑Mine AISC ≈US$1,890/oz.
  • Funding: Project to be fully funded from Thor’s cash reserves and existing project financing.
  • Environmental Approval: Senegal Ministry of Environment approved the ESIA in January 2026.
  • Next Steps: Finalize Mining Convention with Senegal government; detailed design, long‑lead item orders, and EPC contract award targeted for H1 2026. First production expected early 2028.

MRE Highlights * Indicated Mineral Resource: 50.6 Mt @ 1.04 g/t Au = 1.7 Moz Au (gold price US$4,000/oz).
Inferred Mineral Resource: 9.3 Mt @ 0.92 g/t Au = 273,000 oz Au (gold price US$4,000/oz).
Probable Reserve: 36.6 Mt @ 1.03 g/t Au = 1.2 Moz Au (gold price US$3,000/oz).
* Resource includes Makosa, Makosa Tail, and initial Baraka 3 prospect results; remains open along strike and down‑dip.

Exploration Update * Ongoing 40,000 m drilling program throughout 2026 to delineate additional oxide ore across the Douta permit area and adjacent permits (Douta West, Bousankhoba).