Northwire Canada EditionWednesday, July 29, 2026
Northwire
ZAC 0.060 +0.0% ELE 21.18 −1.7% GHRT 0.750 +0.0% AEM 203.13 +0.1% JTWO 0.135 +0.0% EDR 10.63 −2.8% VMXX 0.750 +5.6% K 32.71 −1.5% AGI 40.13 −1.4% VGZ 2.40 +0.8% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% ZAC 0.060 +0.0% ELE 21.18 −1.7% GHRT 0.750 +0.0% AEM 203.13 +0.1% JTWO 0.135 +0.0% EDR 10.63 −2.8% VMXX 0.750 +5.6% K 32.71 −1.5% AGI 40.13 −1.4% VGZ 2.40 +0.8% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0%
Financings

Austral obtains $1M (U.S.) loan from Argentine bank

AGLD · Price

Executive Summary

  • Austral Gold’s Casposo Argentina branch secured a new US$1 million short‑term loan from Banco San Juan SA.
  • The loan will fund working capital as the Casposo processing plant moves from refurbishment into commissioning.
  • Loan terms: 180‑day term, 8.5% annual interest, unsecured, repayment at maturity from mineral export proceeds.

Key Details

  • Loan amount: US$1 million (unsecured).
  • Lender: Banco San Juan SA (Argentina).
  • Term: 180 days from disbursement.
  • Interest rate: 8.5% per annum.
  • Repayment: Lump‑sum at maturity, financed by proceeds from mineral exports; early repayment option available.
  • Use of proceeds: Working capital for Casposo Argentina Ltd. after completion of major plant refurbishments.
  • Recent upgrades to Casposo processing plant (since July 31 2025):
  • Relining and installation of a semi‑autogenous grinding (SAG) mill.
  • Installation of a new hydrocyclone.
  • Substantial refurbishment of the filter band.
  • Previous financing: Banco San Juan previously provided a US$7 million loan facility in December 2024.

Notable Quotes

(No direct quotes were included in the release.)

Read the original news release →

More from Austral Gold Limited