Selkirk Copper Completes Phase 1 Drill Program and Assumes Site Responsibility for Minto Copper-Gold-Silver Mine
Selkirk Copper Advances Minto Restart Plan with Drill Completion and Site Takeover

Executive Summary
- Drill Program Completion: Selkirk Copper has completed its Phase 1 drill program at the Minto Mine, totaling 52,288 metres across 175 holes (exceeding the original 50,000m plan).
- New Discovery: A new mineralized lens was discovered in Area 118, located approximately 120 meters below previously known resources.
- Operational Control: As of April 1, 2026, the company assumed site operations and care-and-maintenance responsibilities from the Yukon Government.
- Next Steps: Geological modelling for an updated Mineral Resource Estimate is expected in June 2026, followed by a Preliminary Economic Assessment (PEA) mid-2026.
- Restart Timeline: The site transition supports a potential restart decision targeted for mid-2027.
Material Impact
- Execution Confirmation: The completion of the drill program validates the company's ability to execute its exploration plan, which was previously scheduled for early 2026. This reduces execution risk regarding resource definition.
- Operational Shift: Assuming site responsibility from the Yukon Government is a tangible milestone that moves the project from "care and maintenance" status to active development control. However, this also transfers operational liabilities and costs to the company.
- Resource Upside: The discovery of a new lens in Area 118 adds potential upside to the resource model prior to the PEA. However, only 48% of assay results have been released as of April 15, meaning full economic implications are not yet quantified.
- Market Expectations: Given the significant price appreciation from $0.16 (April 2025) to $1.47 (April 2026), much of this progress appears priced in. The news confirms existing guidance rather than introducing a fundamentally new catalyst like a PEA result or Feasibility Study.
- Financing Context: This follows a $20 million bought-deal financing on April 9, 2026, which provides capital for the development phase but introduces dilution risk.
SCMI · Price
Company Overview
- Company Name: Selkirk Copper Mines Inc. (formerly Venerable Ventures Ltd.).
- Flagship Project: Minto Copper-Gold-Silver Mine, located in central Yukon (~250 km north of Whitehorse).
- Project Status: Restart phase; transitioning from care and maintenance to active development.
- Infrastructure: Existing 4,100 t/d processing plant, open-pit and underground mine infrastructure, power line, water treatment facilities, and road/barge access valued at >C$300M historically.
- Production Target: First production anticipated mid-2028 with a design throughput of 4,100 tpd (~1.5 Mtpa).
- Mine Life Goal: Targeting a 12–15 year operational life post-restart.