Northwire Canada EditionFriday, November 13, 2026
Northwire
⌕
Gold 3,885.30 −2.9% Silver 50.06 −3.7% Copper 6.19 −1.5% Oil 88.70 +2.5% Palladium 992.00 −5.2% SEA 35.00 −3.2% GLO 0.300 −6.2% WM 1.42 −2.1% MFG 3.25 −4.7% RAGE 0.295 +0.0% DPM 50.56 −4.2% ARIS 21.08 −4.7% AUEN 0.170 +6.2% FCI 0.540 −1.8% SLI 1.98 −5.3% COCO 0.350 −4.1% BCU 0.060 +0.0% BGF 0.025 +0.0% TDG 0.710 +44.9% PRU 6.04 −4.1% NGEX 21.01 −5.2% Gold 3,885.30 −2.9% Silver 50.06 −3.7% Copper 6.19 −1.5% Oil 88.70 +2.5% Palladium 992.00 −5.2% SEA 35.00 −3.2% GLO 0.300 −6.2% WM 1.42 −2.1% MFG 3.25 −4.7% RAGE 0.295 +0.0% DPM 50.56 −4.2% ARIS 21.08 −4.7% AUEN 0.170 +6.2% FCI 0.540 −1.8% SLI 1.98 −5.3% COCO 0.350 −4.1% BCU 0.060 +0.0% BGF 0.025 +0.0% TDG 0.710 +44.9% PRU 6.04 −4.1% NGEX 21.01 −5.2%
Production / Operations

Patagonia Gold recaps construction work at Calcatreu

PGDC · Price

Executive Summary

  • Patagonia Gold Corp. provided a construction and operational update on its Calcatreu project in Argentina, confirming that construction commenced in Q1 2025 following permit receipt.
  • Mining activities began in August 2025 with topsoil removal, and the first blast occurred in September 2025. The company expects to commence first leaching in Q1 2026.
  • Key infrastructure milestones include the completion of the explosives magazine, chemical storage facility, and the first section of the leach pad. The carbon-in-column plant section is nearing completion, with temporary tolling arrangements for downstream processing established.

Key Details

  • Project Location & Geology: Located in Rio Negro, Argentina, 85 km south of Ingeniero Jacobacci. It is a low-sulphidation, epithermal gold and silver system with surface outcropping.
  • Resource Estimates: Total measured and indicated mineral resources are estimated at 9.84 million tonnes at an average grade of 2.11 g/t gold and 19.8 g/t silver, yielding 669,000 ounces of gold and 6.3 million ounces of silver.
  • Construction & Infrastructure Status:
    • Explosives: Magazine completed in August 2025 with 75-tonne capacity; blasting service outsourced to Enaex.
    • Leach Pad: First section completed; electric leak location tests scheduled for January 2026. Loading of stockpiled material is planned for January 2026.
    • Chemical Storage: Facility completed in December 2025 with 120-tonne capacity. 80 tonnes of product arrived on-site on Dec. 23, 2025.
    • Processing Plant: Carbon-in-column section nearing completion (expected Jan 2026). Components from FL Smith have arrived and been erected.
    • Downstream Processing: Due to incomplete downstream components, loaded carbon will be temporarily transported to Santa Cruz facilities on a tolling basis. Dore will be returned to Rio Negro for shipment to refinery. Downstream components expected to be operational at the project approx. six months after commencing operations.
    • Camp & Power: Camp capacity for 192 people nearing completion (half commissioned). Power sourced from three 1-MW diesel generators (installed/tested) with 140,000 litres fuel storage.
  • Operational Timeline:
    • Q4 2024: Permits received.
    • Q1 2025: Construction commenced.
    • August 2025: Mining activities commenced (topsoil removal).
    • September 2025: First blast made.
    • December 2025: Chemical storage facility completed; chemicals arrived.
    • January 2026: Leach pad leak tests, material loading, and carbon-in-column completion expected.
    • Q2 2026: New NI 43-101 technical report (updating resources/reserves) expected to be released.
  • Employment & Community: 135 employees currently, mostly recruited locally from Ingeniero Jacobacci or Rio Negro. Company maintains regular contact with local authorities and communities.
  • Certification: Company intends to certify the project with the Cyanide Code; auditor visit planned for early January 2026.
  • Technical Report: NCL Ingeniera y Construccion engaged in Q3 2025 to update mineral resource and reserve estimates. The new report will supersede the Dec. 31, 2018 technical report.

Notable Quotes

  • No direct quotes from the CEO/President were included in the provided text.
Read the original news release →

More from Patagonia Gold Corp.