B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Production / Operations

Electra talks North American cobalt refinery progress

ELBM · Price

Executive Summary

  • Electra Battery Materials Corp. provided a progress update on the construction of North America's first cobalt sulphate refinery, highlighting significant milestones in civil works and infrastructure.
  • The company confirmed that construction financing, permits, and the majority of long-lead equipment are secured, with the project targeting a 2027 commissioning date.
  • Current site activities focus on civil, structural, concrete, and tankage installation, while preparing for the integration of mechanical systems and the mobilization of larger construction crews.

Key Details

  • Project Status: Construction is underway at North America's first cobalt sulphate refinery.
  • Completed Work: Installation of exterior pipe racks connecting the leach plant, solvent extraction (SX) building, and crystallizer is complete.
  • Current Activities: Site work is centered on civil, structural, concrete, and tankage installation.
  • Infrastructure Completion: New parking areas, additional power services, construction trailers, laydowns, and owners team office areas are nearly complete.
  • Procurement & Planning: Key suppliers and contractors are engaged to support detailed execution planning, budget refinement, and schedule adjustments.
  • Financial & Regulatory Status: Construction financing and permits are in place; the majority of long-lead equipment is secured.
  • Future Milestones: Efforts are focused on sequencing work and preparing for the integration and installation of mechanical systems.
  • Target Date: The project aims for a 2027 commissioning.
  • Strategic Context: The refinery supports the company's strategy to build a resilient North American critical minerals supply chain, producing battery-grade cobalt to support domestic supply reliability.

Notable Quotes

  • "Momentum continues to build across the project... Strong planning and close collaboration with our partners are translating into tangible progress on the ground. We are excited by how the project is coming together and remain fully focused on delivering this important facility efficiently and safely." — Paolo Toscano, vice-president, projects and engineering.
Read the original news release →