Buffalo Potash Connects Second Producer Well and Establishes Fluid Communication Between All Horizontal Wells
Buffalo Potash confirms all three IPM wells are in fluid communication, with brine-to-surface operations now the next operational milestone.

Buffalo Potash Corporation (BUFF) has confirmed the second of two producer-well connections at the Disley Initial Production Module (IPM), completing the fluid-communication path between the central injector (1D15-10) and both producers (5D15-10, 4D15-10). This development is technical and underground in scope, involving no production, revenue, grade, or flow rate, and does not alter the company’s Q1 2027 first-production target.
All three horizontal wells are now connected through the "Mining Plane," an underground flow path along the basal Belle Plaine clay seam. The second connection was achieved using the same method as the first, which was announced on November 23, 2026, and formed horizontally along the target clay seam in consistency with the rock-mechanics model. The Mining Plane now extends on both sides of the injector, with management estimating the surface area is "substantial" and sufficient for solution mining, though no specific area figure or volumetric estimate was quantified.
The next step involves optimizing the Mining Plane by using the 11-stage packer system to pressurize different points along the wells, growing KCl contact area before circulating brine to surface. The company expects to report brine flow rates and grade when this occurs, but provided no specific date. Each horizontal well features a 565 m lateral and 11-stage packers. Phases 1 and 2, covering source and disposal wells as well as HLD drilling, are complete. Phase 3 (brine circulation) and Phase 4 (site development) are in progress, while Phase 5 (surface processing) is pending, with equipment engineering being finalized and procurement commenced.
Unchanged economics for the IPM include 125,000 TPA of soluble-grade potash and an estimated ~12-month standalone payback. Full build-out up to 1,125,000 TPA is projected to yield an after-tax NPV of US$1.1B at 8% and an IRR of 30%, based on a PEA dated May 21, 2026, effective April 15, 2026. Regarding royalty financing, definitive documentation with Altius Royalty Corporation is still being advanced. The total financing is C$8.5M, of which C$3.4M is due at closing and C$5.1M is tied to brine-circulation technical conditions.
The company disclosed that the production decision is not based on a feasibility study with mineral reserves. The PEA includes inferred resources, carrying a higher risk of economic and technical failure.
Buffalo Potash Corporation (BUFF) completed the connection of its second producer well on November 25, 2026, following the initial connection announced on November 23. The company had previously indicated it was applying lessons learned from the first well to connect the second producer well.
The successful connection of a second independently formed horizontal well along the same seam provides evidence of repeatability. Both connections matched the rock-mechanics model, supporting the predictive value of the work for future well pairs. This achievement removes the operational uncertainty associated with the second connection, which had previously posed a risk to the Integrated Production Model (IPM) timeline had it failed or formed in the wrong plane.
Management described the connected area as having "substantial surface area" and being "sufficient for solution mining," expressing confidence in the results. However, the release did not disclose specific pressure data, connection times, area measurements, or brine chemistry. The true test of the project remains brine circulation to surface with a saleable grade and flow rate, a technical challenge distinct from the establishment of the well connections.
The announcement did not alter the project’s schedule, which targets Q1 2027, nor did it change the planned capacity of 125,000 tonnes per annum (TPA), capital expenditure estimates, Preliminary Economic Assessment (PEA) economics, or the funding conditions set by Altius. The second C$5.1 million tranche from Altius remains linked to the milestone of brine circulation and was not unlocked by this news.
Buffalo Potash shares closed at C$0.61 on November 20, prior to the sequence of connections, and rose to C$0.80 on November 24. The price increase occurred largely during the connection sequence, with the subsequent news offering limited additional information.
Buffalo Potash Corporation (TSXV: BUFF, OTCQB: BLPTF, FSE: VU5) is a pre-revenue Saskatchewan potash developer that began trading on January 6, 2026, following a December 2025 reverse takeover. The company’s flagship asset is the Disley Project, located approximately 50 km northwest of Regina. The property covers 10,610 hectares of Crown and freehold mineral rights and is situated immediately east of K+S Bethune and north of Mosaic Belle Plaine, two of the world’s largest potash solution mines.
Buffalo Potash utilizes a patented Horizontal Line-Drive (HLD) selective solution mining technology. This method employs a central horizontal injector with producers on either side, placed along the basal Belle Plaine clay seam. The approach uses oilfield-style horizontal drilling and multi-stage packers rather than conventional vertical caverns, aiming for fewer wells, reduced freshwater usage, lower capital intensity, and modular scalability.
A maiden Mineral Resource Estimate released in April and May 2026 reported Measured and Indicated resources of 1,667 Mt KCl at 34.8% KCl, containing 581 Mt of contained KCl. Inferred resources total 2,663 Mt at approximately 35.0% KCl. No mineral reserves have been established.
The development plan outlines three facilities: the 125,000 TPA IPM, followed by Disley East and Disley West at 500,000 TPA each, for a total capacity of up to 1,125,000 TPA. A Preliminary Economic Assessment (PEA) effective April 15, 2026, and dated May 21, 2026, by Micon International, estimated an after-tax NPV of US$1.1B at an 8% discount rate and an IRR of 30%. Initial CAPEX is projected at US$639M, including US$128M in contingency, with OPEX at US$55/t. Price assumptions are based on US$394/t for granular MOP and US$374/t for soluble grade.
Recent operational milestones include the drilling of five IPM wells, completed on September 25, 2026. Regulatory progress included an EIA exemption on September 17, 2026, and Permit PC26-153 on October 16, 2026. Brine injection commenced on October 28, 2026, with the first connection established on November 23, 2026, and a second connection on November 25, 2026.
Assays released on March 10, March 25, and October 14, 2026, confirmed high-grade sylvinite, including 20.5 m at 39.4% KCl in the 15-10 well. In February 2026, 108 m of core from 7-10 confirmation holes showed greater than 98% recovery. The company has also conducted 3-D seismic surveys and legacy core reassays. The IPM is being constructed without a feasibility study or established reserves.