Buffalo Potash Achieves First Fluid Connection Between Horizontal Wells at Disley
Buffalo Potash’s first producer connection validates the HLD deposit, with a second link currently pending completion.

Buffalo Potash Corporation (TSXV: BUFF) announced the first fluid connection between the central injector well (1D15-10) and the first producer well (5D15-10) at the Disley Initial Production Module. The connection was established following the commencement of brine injection on October 28, 2026. According to management, wellhead fluid and pressure readings are consistent with the company’s rock-mechanics model, indicating that the connection formed horizontally along the target basal Belle Plaine clay seam.
The company stated that this milestone establishes an initial “Mining Plane,” which management estimates has substantial surface area sufficient for solution mining. Buffalo Potash plans to optimize the plane and work on connecting the second producer well (4D15-10) before bringing brine to the surface. The technical scope of the operation involves three parallel horizontal wells, each featuring a 565-metre lateral and an 11-stage packer system. These packers allow for independent stage pressurization to adjust the mining plane.
The release did not disclose brine flow rates, KCl grades, recovery figures, production rates, capital cost updates, or any changes to the Q1 2027 first-production target. Additionally, the company confirmed that Altius royalty documentation is still being advanced. The Preliminary Economic Assessment (PEA) remains unchanged, projecting an after-tax net present value (NPV) of US$1.1 billion at an 8% discount rate, an internal rate of return (IRR) of 30%, and an estimated payback period of 12 months from the start of production for the Initial Production Module (IPM). The IPM capacity is estimated at 125,000 tonnes per annum (TPA), with full build-out reaching up to 1,125,000 TPA.
Buffalo Potash listed on the TSXV in January 2026, subsequently receiving well licences and completing confirmation drilling and assays. The company delivered its maiden Mineral Resource Estimate (MRE) and PEA in April 2026, followed by a C$14.85 million private placement in June 2026. Drilling of all five IPM wells was completed through August-September 2026, and the IPM permit was received in October 2026. Brine injection began on October 28, 2026, leading to the current achievement of the first producer connection, a sequence that has broadly tracked prior guidance. The release reiterated that the IPM production decision is not based on a feasibility study with mineral reserves and that the Horizontal Longhole Drilling (HLD) method has not been operated at commercial scale.
Buffalo Potash Corporation (BUFF) reported a positive technical development with the connection of its first producer well, confirming the company’s operational model. This milestone follows the brine-injection announcement made on October 28 and represents the anticipated next step in the project’s execution.
The new data provided is limited to wellhead pressure and fluid interpretation, alongside management’s estimate of an initial mining plane. The release did not include an independent flow test, KCl grade results, brine-to-surface outcomes, or an economic update.
The announcement supports the company’s execution credibility, as it has progressed from drilling to completions, brine injection, and the first connection without disclosing any timeline slips. The company maintains its target for first production in Q1 2027 and its PEA economics remain unchanged.
Commercial proof is deferred until the second producer connection, brine-to-surface flow, grade verification, and sustained solution mining performance are disclosed. Until these metrics are confirmed, the risk of technical failure remains material.
Additionally, the disclosed Altius royalty is still in the definitive-documentation stage. The C$5.1 million second tranche is tied to brine-circulation conditions that have not yet been satisfied.
Buffalo Potash Corporation (TSXV: BUFF, OTCQB: BLPTF, FSE: VU5) is a Saskatchewan-based potash developer focused on commercializing its patented Horizontal Line-Drive selective solution mining method. The company is currently pre-revenue and holds its flagship Disley Project, located approximately 50 km northwest of Regina. The property covers 10,610 hectares and is situated adjacent to the K+S Bethune and Mosaic Belle Plaine solution mines.
The company’s development plan centers on an Initial Production Module designed to produce 125,000 tonnes per annum (TPA) of soluble-grade potash, with first production targeted for the first quarter of 2027. A full build-out would include the Disley East and Disley West expansions, potentially increasing capacity to up to 1,125,000 TPA.
Regarding resources, the maiden Mineral Resource Estimate (MRE) identified measured and indicated resources of 1,671.5 million tonnes (Mt) at a grade of 34.8% KCl, containing approximately 582 Mt of KCl. Inferred resources total 2,663.2 Mt at 34.96% KCl. No mineral reserves have been established.
A Preliminary Economic Assessment (PEA) dated May 21, 2026, outlined financial metrics for the project. The study reported an after-tax net present value (NPV) of US$1.1 billion at an 8% discount rate, with an internal rate of return (IRR) of 30%. Pre-tax metrics included an NPV of US$1.535 billion and an IRR of 35%. Initial capital expenditure was estimated at US$639 million, including contingency, with sustaining capital of US$483 million and operating expenditure (OPEX) of US$55 per tonne. The presentation cited a full-project payback period of 2.9 years, while the release indicated a payback of approximately 12 months for the standalone Initial Production Module.
No analyst ratings, price targets, or consensus estimates are provided in the materials.