Production / Operations
Inside America's Largest Conventional Measured and Indicated Uranium Deposit: Eagle Nuclear Energy Advances Aurora Toward Pre-Feasibility

DML · Price
Executive Summary
- Eagle Nuclear Energy has commenced environmental baseline studies at its flagship Aurora Uranium Project, located on the Oregon-Nevada border.
- The studies are a precursor to a major 27,000-foot, 47-hole drilling program scheduled to begin in July 2026.
- The company is advancing the project toward a Pre-Feasibility Study (PFS) targeted for the second half of 2027.
Key Details
- Aurora Uranium Project Resources: Contains 32.75 million pounds of indicated uranium and 4.98 million pounds of inferred uranium under the SK-1300 TRS reporting standard.
- Drilling Program Specifications:
- Total footage: 27,000 feet.
- Scope: 47 holes.
- Schedule: Commencing early July 2026.
- Duration/Equipment: Estimated 3-to-4 month period using two to three drill rigs.
- Contractors and Partners:
- Drilling Services: Harris Exploration Drilling & Associates Inc. (contracted up to three track-mounted core drill rigs).
- Resource Consultants: BBA USA Inc. (designed the drill program and conducted gap analysis).
- Permitting: SLR International Corporation (leading the permitting effort).
- Additional Assets: The company also holds the adjacent Cordex deposit, which offers potential for resource expansion beyond the Aurora project.
- Market Context: Spot uranium pricing was approximately $86.55 per pound as of May 1, 2026.