Gold 4,079.60 −0.8% Silver 51.94 −0.8% Copper 6.24 −0.5% Oil 90.83 +0.3% Palladium 1,017.10 −2.6% KRN 0.260 −7.1% GSKR 2.84 +5.6% ADE 0.125 +4.2% NRM 0.055 +0.0% BBB 0.520 −1.9% LGD 2.09 +1.9% DEC 0.110 +0.0% LCE 0.200 +0.0% NILI 0.515 −1.0% CDE 21.85 +6.7% CAN 0.045 +0.0% LORD 0.100 +0.0% HBM 29.49 +2.3% ELEF 0.265 +120.8% MUN 0.300 +0.0% SAGA 0.400 +6.7% Gold 4,079.60 −0.8% Silver 51.94 −0.8% Copper 6.24 −0.5% Oil 90.83 +0.3% Palladium 1,017.10 −2.6% KRN 0.260 −7.1% GSKR 2.84 +5.6% ADE 0.125 +4.2% NRM 0.055 +0.0% BBB 0.520 −1.9% LGD 2.09 +1.9% DEC 0.110 +0.0% LCE 0.200 +0.0% NILI 0.515 −1.0% CDE 21.85 +6.7% CAN 0.045 +0.0% LORD 0.100 +0.0% HBM 29.49 +2.3% ELEF 0.265 +120.8% MUN 0.300 +0.0% SAGA 0.400 +6.7%
Production / Operations

Inside America's Largest Conventional Measured and Indicated Uranium Deposit: Eagle Nuclear Energy Advances Aurora Toward Pre-Feasibility

DML · Price

Executive Summary

  • Eagle Nuclear Energy has commenced environmental baseline studies at its flagship Aurora Uranium Project, located on the Oregon-Nevada border.
  • The studies are a precursor to a major 27,000-foot, 47-hole drilling program scheduled to begin in July 2026.
  • The company is advancing the project toward a Pre-Feasibility Study (PFS) targeted for the second half of 2027.

Key Details

  • Aurora Uranium Project Resources: Contains 32.75 million pounds of indicated uranium and 4.98 million pounds of inferred uranium under the SK-1300 TRS reporting standard.
  • Drilling Program Specifications:
    • Total footage: 27,000 feet.
    • Scope: 47 holes.
    • Schedule: Commencing early July 2026.
    • Duration/Equipment: Estimated 3-to-4 month period using two to three drill rigs.
  • Contractors and Partners:
    • Drilling Services: Harris Exploration Drilling & Associates Inc. (contracted up to three track-mounted core drill rigs).
    • Resource Consultants: BBA USA Inc. (designed the drill program and conducted gap analysis).
    • Permitting: SLR International Corporation (leading the permitting effort).
  • Additional Assets: The company also holds the adjacent Cordex deposit, which offers potential for resource expansion beyond the Aurora project.
  • Market Context: Spot uranium pricing was approximately $86.55 per pound as of May 1, 2026.