B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Earnings

Digi Power X Achieves Positive Net Earnings for Q3 2025 and Reports Strong Balance Sheet to Support 2026 AI Infrastructure Development Plan

DGX · Price

Executive Summary

  • Digi Power X reported its Q3 2025 unaudited results, turning a $0.3 M net profit and generating $1.9 M EBITDA versus a loss in the prior year.
  • The company’s working capital surged to $15.1 M (up 2,731% YoY) and cash & digital‑currency holdings now exceed $90 M, representing over one‑third of market cap.
  • Operational highlights include the start of an ARMS 200 AI data‑center pod, approval for an additional 60 MW load in New York, and a partnership with Super Micro to deploy its first NVIDIA B200 GPU cluster by Q1 2026.

Key Details

  • Financial Highlights (Q3 2025 vs Q3 2024)
  • Working capital: $15.1 M vs $0.5 M (+2,731%).
  • Net income: $0.3 M vs –$6.4 M.
  • EBITDA*: $1.9 M vs –$2.5 M.
  • Adjusted EBITDA*: $0.8 M vs –$0.96 M.
  • Energy sales revenue: $8.7 M (↑112% YoY).

  • Digital‑Currency Position

  • BTC holdings: 97 BTC ($11.2 M) – up 143% quarter‑over‑quarter.
  • ETH holdings: ~1,000 ETH ($4.2 M).
  • Total digital‑currency value: $15.4 M (↑213% YoY).

  • Capital Expenditures

  • Q3 2025 capex: $3.1 M (vs $1.5 M in Q3 2024).
  • YTD capex: $9.5 M on data‑center infrastructure and AI‑ready equipment.

  • Debt & Liquidity

  • All long‑term debt eliminated; accounts payable reduced by >$3.8 M since year‑end 2024.
  • Cash, BTC, ETH & cash equivalents: >$90 M (≈33% of market cap).

  • Operational / Strategic Updates

  • ARMS 200 Pod: Assembly began Q4 2025; full activation expected Q1 2026.
  • Load Study Approval: Additional 60 MW capacity approved for New York site.
  • GPU Cluster: First NVIDIA B200 cluster on schedule for Q1 2026 (partner: Super Micro).
  • NeoCloudz Platform: Retail compute service slated to launch Jan 2026, offering on‑demand GPU compute via a consumer‑grade interface.
  • Power Asset Roadmap: Planned AI‑driven capacity allocation – Q1 2026: 5 MW; Q4 2026 total 55 MW (critical load 40 MW).

  • Guidance & Outlook

  • 2026 Guidance – Blockchain mining at current levels; AI colocation scaling to 40 MW critical IT load; deployment of 1,024 NVIDIA B200/B300 GPUs via NeoCloudz.
  • 2027 Guidance – AI colocation up to 120 MW; GPU‑as‑a‑Service scale‑up to 3,072 GPUs.

  • At‑the‑Market Financing (ATM)

  • Shares issued: 310,130 subordinate voting shares.
  • Gross proceeds: $1,074,451 at $3.46 per share; net proceeds after commissions: $1,039,962.

  • Debt Settlement

  • Previously announced July 3 2025 debt settlement closed; securities issuance subject to a 4‑month‑plus‑1‑day hold period (TSX Venture approval received Nov 6 2025).

Notable Quotes

  • Michel Amar, CEO: “Digi Power X is transforming from a traditional compute operator into a next‑generation AI infrastructure company… We have never been better positioned to lead in high‑density Tier III AI compute.”
  • Alec Amar, President: “NeoCloudz was designed to democratize access to AI compute. We’re giving smaller AI developers, research labs and startups similar infrastructure advantages traditionally reserved for hyperscalers.”
Read the original news release →