GOLD 4180.90 +1.8% SILVER 57.04 +2.1% COPPER 6.54 −1.8% OIL 95.79 +0.7% PALLADIUM 1133.50 +3.4% YGT 0.180 +5.9% EVI 0.500 +0.0% ADZ 0.125 +0.0% MINK 0.075 +0.0% DNO 0.300 +0.0% RRRL 0.150 +0.0% MTT 0.245 +0.0% BAU 0.180 −5.3% TECT 1.70 +2.4% TOM 0.135 +0.0% FVL 0.920 +2.2% HART 0.195 +0.0% VLD 0.415 +0.0% TGOL 0.150 +0.0% TWR 0.170 +0.0% LAF 0.810 +0.0% GOLD 4180.90 +1.8% SILVER 57.04 +2.1% COPPER 6.54 −1.8% OIL 95.79 +0.7% PALLADIUM 1133.50 +3.4% YGT 0.180 +5.9% EVI 0.500 +0.0% ADZ 0.125 +0.0% MINK 0.075 +0.0% DNO 0.300 +0.0% RRRL 0.150 +0.0% MTT 0.245 +0.0% BAU 0.180 −5.3% TECT 1.70 +2.4% TOM 0.135 +0.0% FVL 0.920 +2.2% HART 0.195 +0.0% VLD 0.415 +0.0% TGOL 0.150 +0.0% TWR 0.170 +0.0% LAF 0.810 +0.0%
Other Material +

Digi Power X Signs First AI Revenue Contract - $19.6 Million, 24-Month SubQ AI Agreement, Validating Operational Launch of AI Factory

Digi Power X Secures First AI Revenue Contract, Validating Pivot From Crypto to Compute

Executive Summary
  • On April 20, 2026, Digi Power X announced a 24-month bare metal GPU rental agreement with SubQ AI.
  • Total Contract Value (TCV) is approximately $19.6 million, with an upfront non-refundable payment of ~$2.95 million (15% of TCV).
  • The deal utilizes the NeoCloudz platform featuring NVIDIA Blackwell B300 GPUs (192 GB HBM3e).
  • Infrastructure is deployed at a Tier 3 facility in Alabama with redundant power and cooling.
  • This marks the company's first contracted AI revenue, transitioning from development to commercial operations.
  • Future capacity potential is noted as up to ~$120 million annualized revenue if full deployment (4,000 GPUs) is utilized.
Material Impact
  • Revenue Validation: The announcement moves the company from "building infrastructure" to "generating AI revenue," addressing a key execution risk highlighted in previous quarters.
  • Cash Flow Impact: The $2.95 million upfront payment provides immediate liquidity, reinforcing the strong balance sheet reported in FY2025 ($78.5M cash).
  • Expectation Check: Management had guided for Q1/Q2 2026 revenue launch in January and March updates. This news confirms the timeline but does not exceed the previously guided $120 million annualized potential, making it a validation rather than an upside surprise.
  • Customer Concentration: Reliance on SubQ AI as the first major customer introduces concentration risk until additional contracts are signed.
  • Market Sentiment: The deal removes ambiguity regarding the NeoCloudz platform's commercial viability, likely reducing speculative discounting associated with pre-revenue infrastructure plays.
DGX · Price
Company Overview
  • Overview: Digi Power X Inc. is transitioning from cryptocurrency mining to AI infrastructure and energy solutions. It operates data centers in Alabama, New York, and North Carolina.
  • Flagship Project: NeoCloudz GPU-as-a-Service platform utilizing ARMS 200 modular Tier 3 data center pods.
  • Development Status: First ARMS 200 pod commissioned March 2026; first AI revenue contract signed April 2026.
  • Power Assets: Secured ~400 MW of power capacity across three states (Alabama, NY, NC). Includes hydroelectric approval in Upstate New York.
  • Strategic Shift: Intentional pivot from crypto mining revenue (down to $3.5M in FY25) to AI colocation and compute services.