VZZ 0.180 +2.9% BMR 0.145 +3.6% NVO 0.055 −8.3% PMET 4.47 +2.0% CTG 0.125 +13.6% AVU 0.040 +0.0% SGML 14.32 −3.1% WRLG 0.720 +1.4% CAN 0.065 +8.3% ABRA 15.63 +1.6% LSTR 0.060 +0.0% OLA 13.10 +2.5% EQX 13.15 +2.7% SRA 0.780 +0.0% UTWO 0.390 −13.3% IVN 10.64 −1.2% VZZ 0.180 +2.9% BMR 0.145 +3.6% NVO 0.055 −8.3% PMET 4.47 +2.0% CTG 0.125 +13.6% AVU 0.040 +0.0% SGML 14.32 −3.1% WRLG 0.720 +1.4% CAN 0.065 +8.3% ABRA 15.63 +1.6% LSTR 0.060 +0.0% OLA 13.10 +2.5% EQX 13.15 +2.7% SRA 0.780 +0.0% UTWO 0.390 −13.3% IVN 10.64 −1.2%
Production / Operations

Aduro Clean Technologies Provides Update on NGP Pilot Plant Commissioning

ACT · Price

Executive Summary

  • Aduro Clean Technologies reports that its Next Generation Process (NGP) Pilot Plant in London, Ontario has moved from Phase 1 to Phase 2 commissioning on schedule.
  • Core modules—including the extruder, Zeton‑fabricated process skids, and Siemens automation network—are installed and undergoing staged testing, wet runs, and system tuning through mid‑December 2025.
  • Operator training and development of standard operating procedures are underway to prepare for continuous operation and future scale‑up toward the planned 8,000 t/yr Demonstration Plant.

Key Details

  • Phase Transition: Phase 1 (assembly, installation, SAT/FAT) completed; Phase 2 commissioning began in October 2025.
  • Equipment Status:
  • Extruder – Site Acceptance Test (SAT) successfully completed.
  • Process skids (Zeton Inc.) – Factory Acceptance Testing (FAT) passed and shipped to site.
  • Siemens Canada – Automation, control, and communication systems installed; ongoing calibration and validation.
  • Commissioning Activities (Phase 2): Sequential testing, subsystem verification, wet runs, process tuning scheduled through November–mid‑December 2025.
  • Operator Readiness: Planned training sessions and development of standardized operating procedures to ensure readiness for continuous plant operation.
  • Purpose of Pilot Plant: Validate Hydrochemolytic™ Technology in continuous mode, establish operating parameters across target feedstocks, generate product samples and quality data, confirm mass/energy balances, yields, controllability, and support environmental assessments and lifecycle analyses.
  • Future Outlook: Data and experience from Phase 2 will inform design basis and integration approach for the Demonstration Plant (8,000 t/yr capacity).
  • Key Partners: Zeton Inc. (process skids fabrication & integration) and Siemens Canada (automation & control systems) remain actively engaged during commissioning.

Notable Quotes

“The NGP Pilot Plant represents the first‑in‑kind implementation of our Hydrochemolytic™ Technology…the data and experience gained will provide critical insight …and bring us closer to commercialization.” – Ofer Vicus, CEO

“As we progress through phase 2 commissioning, our focus remains on verifying performance, ensuring reliability, and completing operator training so that we enter the next stage of operation with confidence.” – David Weizenbach, COO