Gold 3,885.10 −0.0% Silver 49.03 −2.1% Copper 6.08 −1.9% Oil 88.93 +0.2% Palladium 1,004.50 +1.3% BMR 0.165 +0.0% CLV 0.120 + VUL 0.360 −5.3% LUNR 15.46 −4.4% XTG 2.08 +4.0% RUA 1.08 −1.8% TUF 0.620 +0.0% NEXG 1.12 −1.8% ELEF 0.280 +0.0% LVG 0.345 +1.5% BBB 0.510 +2.0% NGC 0.055 −8.3% ABRA 10.54 −2.2% OBUL 0.345 +0.0% MKO 10.53 −2.7% SGML 7.18 +1.4% Gold 3,885.10 −0.0% Silver 49.03 −2.1% Copper 6.08 −1.9% Oil 88.93 +0.2% Palladium 1,004.50 +1.3% BMR 0.165 +0.0% CLV 0.120 + VUL 0.360 −5.3% LUNR 15.46 −4.4% XTG 2.08 +4.0% RUA 1.08 −1.8% TUF 0.620 +0.0% NEXG 1.12 −1.8% ELEF 0.280 +0.0% LVG 0.345 +1.5% BBB 0.510 +2.0% NGC 0.055 −8.3% ABRA 10.54 −2.2% OBUL 0.345 +0.0% MKO 10.53 −2.7% SGML 7.18 +1.4%
Production / Operations

Orezone Reports First Gold from Bombore Hard Rock Expansion

ORE · Price

Executive Summary

  • Orezone Gold completed the first gold pour from its new 2.5 Mtpa hard‑rock expansion at Bomboré, marking the start of commercial production.
  • Mill throughput averaged 78 % of nameplate capacity during the initial five days of operation.
  • The company projects a 45 % increase in total Bomboré gold output to 170,000–185,000 oz in 2026, with commercial production expected to be declared in early Q1‑2026.

Key Details

  • First gold pour achieved on December 15, 2025 after approximately 12 months of construction for the stage 1 hard‑rock expansion.
  • Plant commissioning is complete; initial mill throughput was 78 % of nameplate capacity over the first five days.
  • Expected commercial production declaration in early Q1‑2026.
  • Forecasted total Bomboré production (oxide + stage 1 hard rock) for 2026: 170,000–185,000 oz, a ~45 % increase versus prior levels.
  • The expansion is expected to generate a significant cash‑flow inflection point, supported by the company’s strong balance sheet and high gold prices.
  • Stage 2 of the hard‑rock expansion is underway, projected to lift annual production further to 220,000–250,000 oz once completed.

Notable Quotes

“Commissioning of this plant is now complete, with mill throughput averaging 78% of nameplate capacity for the first 5 days of operations, resulting in first gold on December 15.” – Patrick Downey, President & CEO

“Commercial production is expected to be declared in early Q1‑2026… overall gold production at Bomboré set to increase by 45% to 170,000‑185,000 oz in 2026.” – Patrick Downey, President & CEO

Read the original news release →