LUG 81.27 +2.4% ETG 2.65 +1.1% ARIC 0.860 +2.4% ABC 0.020 +0.0% WEC 0.010 +0.0% NTB 0.020 +0.0% URC 3.83 −8.2% BEX 0.085 +6.2% SUM 1.32 +0.0% FMN 0.270 +10.2% PHNM 0.405 +12.5% HDRO 1.11 −6.7% PWM 0.620 −1.6% LIO 0.155 +10.7% NTH 0.160 +1.6% ELEF 0.120 −4.0% LUG 81.27 +2.4% ETG 2.65 +1.1% ARIC 0.860 +2.4% ABC 0.020 +0.0% WEC 0.010 +0.0% NTB 0.020 +0.0% URC 3.83 −8.2% BEX 0.085 +6.2% SUM 1.32 +0.0% FMN 0.270 +10.2% PHNM 0.405 +12.5% HDRO 1.11 −6.7% PWM 0.620 −1.6% LIO 0.155 +10.7% NTH 0.160 +1.6% ELEF 0.120 −4.0%
Production / Operations

Orezone Reports First Gold from Bombore Hard Rock Expansion

ORE · Price

Executive Summary

  • Orezone Gold completed the first gold pour from its new 2.5 Mtpa hard‑rock expansion at Bomboré, marking the start of commercial production.
  • Mill throughput averaged 78 % of nameplate capacity during the initial five days of operation.
  • The company projects a 45 % increase in total Bomboré gold output to 170,000–185,000 oz in 2026, with commercial production expected to be declared in early Q1‑2026.

Key Details

  • First gold pour achieved on December 15, 2025 after approximately 12 months of construction for the stage 1 hard‑rock expansion.
  • Plant commissioning is complete; initial mill throughput was 78 % of nameplate capacity over the first five days.
  • Expected commercial production declaration in early Q1‑2026.
  • Forecasted total Bomboré production (oxide + stage 1 hard rock) for 2026: 170,000–185,000 oz, a ~45 % increase versus prior levels.
  • The expansion is expected to generate a significant cash‑flow inflection point, supported by the company’s strong balance sheet and high gold prices.
  • Stage 2 of the hard‑rock expansion is underway, projected to lift annual production further to 220,000–250,000 oz once completed.

Notable Quotes

“Commissioning of this plant is now complete, with mill throughput averaging 78% of nameplate capacity for the first 5 days of operations, resulting in first gold on December 15.” – Patrick Downey, President & CEO

“Commercial production is expected to be declared in early Q1‑2026… overall gold production at Bomboré set to increase by 45% to 170,000‑185,000 oz in 2026.” – Patrick Downey, President & CEO