GOLD 4383.90 −0.9% SILVER 66.53 −0.9% COPPER 6.79 +1.5% OIL 92.37 −3.9% PALLADIUM 1319.50 +0.0% MSC 0.020 +0.0% BRON 0.050 +0.0% ELD 59.44 −1.4% GBML 0.220 +0.0% SUM 1.59 +0.0% ABC 0.015 +0.0% ELE 30.45 +2.2% CDE 27.46 −0.7% LIB 0.990 +1.0% SLVR 1.17 +0.0% NVO 0.075 −6.2% BRO 0.235 +2.2% FMAN 0.415 +0.0% HVG 0.050 +0.0% MSV 0.540 +16.1% SCD 0.185 −2.6% GOLD 4383.90 −0.9% SILVER 66.53 −0.9% COPPER 6.79 +1.5% OIL 92.37 −3.9% PALLADIUM 1319.50 +0.0% MSC 0.020 +0.0% BRON 0.050 +0.0% ELD 59.44 −1.4% GBML 0.220 +0.0% SUM 1.59 +0.0% ABC 0.015 +0.0% ELE 30.45 +2.2% CDE 27.46 −0.7% LIB 0.990 +1.0% SLVR 1.17 +0.0% NVO 0.075 −6.2% BRO 0.235 +2.2% FMAN 0.415 +0.0% HVG 0.050 +0.0% MSV 0.540 +16.1% SCD 0.185 −2.6%
Production / Operations

K92 Mining Announces Strong Q3 Production Results - 44,323 oz AuEq Produced Plus 4,893 oz AuEq in Commissioning Stockpile and Significant Stage 3 Expansion Progress Achieved

KNT · Price

Executive Summary

  • K92 Mining reported strong Q3 2025 results: 44,323 oz AuEq (42,244 oz gold), 1.32 M lb copper and 34,831 oz silver, exceeding the lower end of its annual guidance.
  • The Stage 3 Expansion plant construction is complete; commissioning is on schedule with first gold pour and concentrate production expected in H1 2024‑Q4 2025.
  • Capital spend for Stage 3 is ~90% committed or expended and remains on budget, de‑risking the expansion and supporting continued throughput growth.

Key Details

  • Production: 44,323 oz AuEq (42,244 oz gold), 1,323,538 lb copper, 34,831 oz silver; sales of 45,006 oz gold, 1,480,151 lb copper, 43,271 oz silver.
  • Ore Processed: 137,172 t (31% YoY increase); head grade 11.2 g/t AuEq (10.7 g/t gold, 0.47 % Cu, 10.3 g/t Ag).
  • Recoveries: Gold 95.0 %, Copper 94.6 % – both above the Updated DFS targets (92.6 % Au, 94.2 % Cu).
  • Material Mined: Total 353,770 t (ore + waste); ore mined 152,485 t across 13 levels; mine development 2,477 m.
  • Stockpile: End‑Q3 commissioning stockpile of 4,893 oz AuEq, meeting Stage 3 Expansion requirements.
  • Stage 3 Expansion: New 1.2 M t/yr process plant construction complete; crushing, grinding and flotation circuits now being commissioned with ore. First gold pour & concentrate production slated for H1 2025‑Q4 2025. 90 % of growth capital spent or committed, on budget.
  • Key Construction Milestones:
  • Material Pass completed – enabled record daily surface tonnage moves (e.g., 6,404 t on Sep 29).
  • Phase 2 ventilation upgrade finished; full upgrade planned for Oct 2025 → +30 % airflow.
  • Phase 3 ventilation (Puma Drive) ~70 m from breakthrough; target Q4 completion.
  • Decline‑Incline Convergence project: 258 m advanced in Q3, <370 m remaining; slated for Q1 2026.
  • Surface tele‑remote loader system operational – 24 h underground loader control from surface.
  • Primary Power Station Phase 1 (8.8 MW) commissioned; Phase 2 to reach 15.2 MW by H1 2026.
  • Future Capital Projects:
  • Pastefill plant contracts awarded; detailed engineering complete, civil works underway.
  • Surface tailings filtration plant design finished; early earthworks started.
  • Stage 4 ventilation upgrade (two 2 MW VSD fans) scheduled for Q4 2025 completion; electrification planned H1 2026.
  • Guidance: On track to meet 2025 production guidance of 160,000–185,000 oz AuEq.

Notable Quotes

“The third quarter marked another strong period of progress… commissioning of the new 1.2 million‑tonne‑per‑annum Stage 3 Expansion Process Plant nearing completion… we are well‑positioned to achieve our 2025 production guidance.” – John Lewins, CEO & Director