Gold 3,886.20 −2.9% Silver 50.03 −3.8% Copper 6.19 −1.5% Oil 88.86 +2.7% Palladium 994.25 −5.0% TDG 0.740 +51.0% PRU 6.07 −3.6% NGEX 21.14 −4.7% TWO 0.370 +0.0% BIG 1.05 +10.5% VCG 1.10 +0.0% SCD 0.145 +0.0% GAL 0.370 −0.7% SAG 0.620 −6.1% VIZ 0.195 +0.0% SAGA 0.370 −7.5% ZEN 0.530 −3.6% GDP 0.230 +0.0% PDN 8.41 +0.0% FL 0.350 −2.8% RIO 2.62 −2.1% Gold 3,886.20 −2.9% Silver 50.03 −3.8% Copper 6.19 −1.5% Oil 88.86 +2.7% Palladium 994.25 −5.0% TDG 0.740 +51.0% PRU 6.07 −3.6% NGEX 21.14 −4.7% TWO 0.370 +0.0% BIG 1.05 +10.5% VCG 1.10 +0.0% SCD 0.145 +0.0% GAL 0.370 −0.7% SAG 0.620 −6.1% VIZ 0.195 +0.0% SAGA 0.370 −7.5% ZEN 0.530 −3.6% GDP 0.230 +0.0% PDN 8.41 +0.0% FL 0.350 −2.8% RIO 2.62 −2.1%
Technical Study

Thesis Gold Files Pre-Feasibility Technical Report for the Lawyers-Ranch Gold-Silver Project

TAU · Price

Executive Summary

  • Thesis Gold filed its NI 43‑101 pre‑feasibility study (2025 PFS) for the wholly owned Lawyers‑Ranch project on SEDAR+.
  • The study reports strong economics: after‑tax IRR of 54.4% and NPV₅% of C$2.37 billion at US$2,900/oz Au and US$35/oz Ag, with a quick payback of ~1.1 years.
  • Highlights include a maiden mineral reserve of 76.16 Mt @ 0.97 g/t Au & 28 g/t Ag (AuEq 1.33 g/t), initial capex of $736.2 M, and average AISC of US$1,185/AuEq oz.

Key Details

  • Report filing: Pre‑feasibility Study (“2025 PFS”) filed on SEDAR+; technical report prepared by Ausenco Engineering Canada ULC et al., compliant with NI 43‑101.
  • Economic assumptions (base case): US$2,900/oz Au and US$35/oz Ag.
  • After‑tax results (base case):
  • IRR 54.4%
  • NPV₅% C$2.37 billion
  • Payback period ≈1.1 years
  • Upside scenario (US$4,100/oz Au & US$51/oz Ag):
  • After‑tax IRR 87.8%
  • NPV₅% C$4.36 billion
  • Production outlook:
  • First three years – average 266,000 AuEq oz/year (payable).
  • 15‑year LOM – average 187,000 AuEq oz/year.
  • Silver contributes ~23% of projected revenue.
  • Mineral reserve: 76.16 Mt containing 0.97 g/t Au and 28 g/t Ag (AuEq 1.33 g/t).
  • Capital expenditure: Estimated initial capex $736.2 M; after‑tax NPV₅%/capex ratio of 3.2:1 (excluding C$91.1 M pre‑production stockpile revenue).
  • All‑in Sustaining Cost (AISC): US$1,185 per AuEq oz (average over LOM).
  • Project upside: Potential for further engineering optimisation in a forthcoming Feasibility Study and untapped exploration potential across the project area.
  • Forward‑looking actions: Environmental Assessment underway; Feasibility Study planned for 2026 to de‑risk and advance the project.

Notable Quotes

“The recently published Prefeasibility Study outlines robust project economics, including a 54.4% after‑tax IRR and an after‑tax NPV₅% of C$2.37 billion…underscoring the Project's strong value‑creation potential.” – Ewan Webster, President, CEO & Director, Thesis Gold Inc.

Read the original news release →

More from Thesis Gold & Silver Inc.