Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.27 +0.5% Oil 86.53 +0.6% Palladium 1,030.00 +0.9% TIG 0.800 +0.0% RVG 0.715 −4.0% FNV 354.26 −2.4% FDY 4.30 −0.5% MAU 16.05 −3.2% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7% Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.27 +0.5% Oil 86.53 +0.6% Palladium 1,030.00 +0.9% TIG 0.800 +0.0% RVG 0.715 −4.0% FNV 354.26 −2.4% FDY 4.30 −0.5% MAU 16.05 −3.2% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7%
Production / Operations

Sixty North Gold Provides Update on Mon Gold Mine Logistics and Development

SXTY · Price

Executive Summary

  • The company’s new 100 tpd mill is on a container ship scheduled to arrive in Canada on February 20, 2026.
  • Construction of the winter access road and delivery of 19 truckloads of supplies (including the mill) are progressing for February‑March shipment.
  • Mill assembly is planned for late April with commissioning targeted for June–July 2026, supporting 24/7 processing of material from the A‑Zone vein and future development of the DD‑Zone and deeper levels.

Key Details

  • Mill Shipment: 100 tpd processing mill loaded on a container vessel; expected landfall in Canada on 20 Feb 2026 (subject to weather).
  • Logistics: 19 truckloads of equipment and supplies, including the mill, will be hauled from Highway 4 (≈20 km east of Yellowknife) to the Mon Gold Mine site during Feb‑Mar 2026.
  • Winter Road: Full length of winter access road from Highway 4 to mine site is under construction and progressing well.
  • Camp Installation: Crews will arrive ahead of mill delivery to set up a new 20‑person trailer camp and clear debris left by the 2023 wildfires that destroyed the previous camp.
  • Equipment Status: Major mining equipment, fuel tanks, and on‑site infrastructure escaped fire damage.
  • Mill Assembly Schedule: Commencement in late April 2026; initial commissioning slated for June–July 2026.
  • Operating Plan: Mill to run 24 hours/day processing ore from the second level of the A‑Zone vein beneath historic stopes.
  • Future Development: DD‑Zone will be evaluated for stope development; main ramp extension planned to reach a third underground level.
  • Technical Review: Release reviewed and approved by Dr. D.R. Webb, President & CEO.

Notable Quotes

“We are pleased to provide an update on our plan to commence gold production this year on our wholly‑owned Mon Gold Mine.” – Dave Webb, President & CEO


Materiality Assessment: Non‑Material – Positive (operational progress update with no immediate financial impact).