Production / Operations
Americas Gold completes phase 1 upgrades at Galena

USA · Price
Executive Summary
- Americas Gold and Silver Corp. completed Phase 1 of the No. 3 shaft upgrade at its wholly‑owned Galena complex in Idaho, finishing four days ahead of schedule.
- The upgrade raised hoisting capacity from ~40 tph to 80 tph in initial operation, with a target of 100 tph once Phase 2 is finished, representing a 100 % productivity improvement.
- New 2,250‑hp spare motor and automation enhancements provide critical backup capacity and de‑risk the mine plan, supporting the company’s growth strategy through 2025.
Key Details
- Upgrade Scope – Phase 1:
- Hoist motor upgraded from 1,750 hp to 2,250 hp, enabling full skips from the deepest level (5600L).
- Installation of a second 2,250‑hp spare motor for primary shaft, adding backup capacity.
- Weight‑measuring systems added to skips to optimize hoisting efficiency.
- Performance Gains:
- Skipping speed increased from 690 ft/min to an estimated 1,200–1,400 ft/min.
- Material handling rose from ~40 tons per hour (tph) to 80 tph in the first days of operation – a 100 % improvement.
- Target post‑Phase 2 capacity: ~100 tph by end‑2025.
- Project Execution:
- Completed during a 10‑day shutdown, four days shorter than the planned 14‑day window.
- Phase 2 scheduled to start before year‑end; expected duration ≈10 days.
- Phase 2 Planned Upgrades:
- Upgrade hoist pads (lilies) and braking system to increase creep times in loading/dump zones.
- Install new hoisting control console with advanced automation capability.
- Deploy a leaky‑feeder antenna system in the shaft to improve underground communications and support future automation.
- Strategic Impact:
- Removes a key bottleneck, boosting overall mine productivity and cost efficiency.
- Provides critical backup capacity, de‑risking the mine plan ahead of planned long‑hole stoping expansion next year.
- Aligns with the company’s ambition to increase silver‑derived revenue to >80 % by end‑2025.
Notable Quotes
- “I am very pleased to announce that the first phase of the Galena No. 3 shaft upgrade has been completed ahead of schedule… we have already reached 80 tons per hour, which is a 100 % improvement on our existing skipping capacity.” – Paul Andre Huet, Chairman & CEO
- “We now have a spare 2,250‑horsepower hoist motor for our primary No. 3 shaft for the first time, providing critical backup capacity and derisking our mine plan.” – Paul Andre Huet