- Ecolomondo’s Hawkesbury TDP facility processed 60 t of crumb rubber over four days, yielding ~24 t recovered carbon black, 6 t syngas and 350 bbl tire‑derived oil.
- September 2025 revenues from the Hawkesbury site rose 325 % versus September 2024, marking a record month for the facility.
- Despite higher output and revenue, the facility remains loss‑making as it continues its ramp‑up phase; the company is hiring additional staff to sustain growth.
Key Details
- Four double batches were run in automatic mode over four consecutive production days.
- Total feedstock processed: 60 tons of crumb rubber.
- Product yields: ≈24 tons recovered carbon black (rCB), 6 tons syngas, 350 barrels tire‑derived oil (equivalent to >2 tanker loads).
- September 2025 revenue increase: +325 % versus September 2024, setting a new monthly record for the Hawkesbury TDP facility.
- Revenue streams include sales of rCB, oil, steel, syngas and tipping fees for scrap‑tire disposal.
- Facility continues to operate at a loss due to its ongoing ramp‑up phase.
- Staffing expansion: hiring and training of additional mechanics, operators, and supervisory personnel across tire shredding, thermal decomposition, and rCB processing departments.
Notable Quotes
“We are proud to achieve this stable and consistent increase in the output at our Hawkesbury facility, particularly in the thermal decomposition department,” – J.F. Labbe, interim CEO.
“It demonstrates the efficiency of Ecolomondo's proprietary TDP technology, and the control system that assures the repetitiveness of the process and the consistency of its end products.” – J.F. Labbe.