Northwire Canada EditionMonday, July 27, 2026
Northwire
B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Resource Estimate

Centerra Gold's Kemess Preliminary Economic Assessment Highlights Strong Economics that Support the Company's Long-Term Growth Pipeline

Centerra Unlocks BC Growth Pillar as Kemess PEA Outlines $1.1 Billion Valuation

Executive Summary

The most recent news (January 19, 2026) details the Preliminary Economic Assessment (PEA) for the Kemess Project in British Columbia. Key highlights include: - After-tax NPV5% of $1.1 billion and an IRR of 16.4% using long-term prices ($2,000/oz gold, $3.75/lb copper). - At spot prices, the NPV5% jumps to $2.75 billion with a 28.7% IRR. - Average annual production of 171,000 ounces of gold and 61 million pounds of copper over a 15-year mine life. - Total Life of Mine (LOM) production of 2.3 million ounces of gold and 851 million pounds of copper. - All-in Sustaining Costs (AISC) on a by-product basis are estimated at a low $971/oz. - Initial capital expenditure is pegged at $771 million, leveraging existing infrastructure (380km power line, 50k tpd mill).

Material Impact

This news is Material - Positive and serves as a critical de-risking event for Centerra’s long-term growth profile. - Strategic Synergy: Kemess provides a second long-life asset in BC, complementing Mount Milligan (recently extended to 2045). This creates a massive operational hub in the Toodoggone district. - Economic Viability: Even at conservative long-term prices, the project shows a billion-dollar valuation. The sensitivity to spot prices is massive, nearly tripling the NPV. - Cost Efficiency: The AISC of $971/oz is significantly lower than Centerra’s consolidated 2025 guidance ($1,650 – $1,750/oz), suggesting Kemess will be a margin-accretive asset. - Capital Intensity: While $771 million is high, Centerra’s $562 million cash balance and zero debt position (as of Q3 2025) suggest they can fund a significant portion from internal cash flow and modest debt if needed, avoiding equity dilution.

CG · Price
Company Overview

Centerra Gold is a mid-tier producer with operations in Canada, Türkiye, and the USA. - Flagship Project (Current): Mount Milligan Mine, BC. A copper-gold open pit producing ~150k oz Au and 60M lbs Cu annually with a mine life extending to 2045. - Key Secondary Asset: Öksüt Mine, Türkiye. A high-margin heap leach operation providing significant free cash flow. - Growth Pillar: Thompson Creek (Moly) and now Kemess (Gold-Copper).

Read the original news release →

More from Centerra Gold Inc.