Drill Results
Pelangio orders CSEM survey for Obuasi, Manfo

PX · Price
Executive Summary
- Pelangio Exploration Inc. has commissioned a deep-penetrating Controlled-Source Electromagnetic (CSEM) survey for its Obuasi and Manfo projects in Ghana, conducted by SEMS Exploration Services.
- The Obuasi survey aims to delineate targets up to one-plus-kilometre depth, specifically searching for conductive and resistive targets that could represent repetitions of the high-grade Obuasi ore shoots extending north-northeast from the AngloGold Ashanti mine.
- The survey will be conducted in tandem with an independent AngloGold Ashanti survey on adjacent property; Pelangio’s portion covers 9.2 square kilometres with 295 stations, while AngloGold Ashanti covers 10.4 square kilometres with 333 stations.
Key Details
- Survey Methodology: CSEM is an active EM method injecting signals into the ground to detect conductive features (sulphide ore) and resistive bodies (gold-bearing quartz lodes) at depths of up to one kilometre or more.
- Equipment: SEMS will use an IRIS Instruments TIP 12000 transmitter powered by a 20-kVA generator, with subsurface responses read by two Metronics magnetotelluric-grade receiver units on a 170-metre grid node spacing.
- Obuasi Project Survey Specs:
- Area: 9.2 square kilometres.
- Stations: 295 stations spaced 170 metres apart.
- Target: Western edge of the property, interpreted to be on strike with the Obuasi mine's main gold trend.
- Context: The northernmost known ore shoot at the Obuasi mine (Far North/Adansi shoot) is located ~4.2 km south-southwest of Pelangio’s boundary at a depth of 700+ metres. Pelangio is testing for potential repetition of these ore shoots.
- Timeline: Tentatively commencing mid-April (pending equipment mobilization from Sweden), requiring ~2 months for field work, followed by one month for 3-D inversion modelling and reporting.
- AngloGold Ashanti Parallel Survey:
- Area: 10.4 square kilometres.
- Stations: 333 stations.
- Relationship: Surveys are independent; no data-sharing agreement has been discussed.
- Manfo Project Survey Specs:
- Timing: To follow the Obuasi surveys.
- Area: 2.8 square kilometres.
- Stations: 100 EM stations.
- Target: Pokukrom deposits and possible downplunge extensions to the northeast; exploring for mineralization deeper than current drill programs.
- Manfo Drilling Update:
- Program: 15-hole, 3,150-metre resource extensional diamond drilling program focused on Pokukrom deposits.
- Status: Three holes are nearly complete.
- Assays: No assays to report as yet.
- Qualified Person: Kevin Thomson, PGeo (Ontario, No. 0191), Senior Vice-President, Exploration, and Director.
Notable Quotes
- None explicitly quoted in the text, though the release notes the belief that if ore shoots repeat into Pelangio's property, they may be comparable to the Far North ore shoot.
More from Pelangio Exploration Inc.
Jun 15, 2026 · 17:31