Executive Summary
- Hive Digital Technologies’ subsidiary, Buzz High Performance Computing, has signed an agreement with Dell Technologies to deploy a 63-node cluster of liquid-cooled servers for its AI cloud expansion.
- Buzz has executed operating agreements for the first phase of deployment within the Bell AI fabric data centre, building on existing partnerships to expand its sovereign AI cloud capabilities.
- The company projects significant growth in GPU capacity and revenue, targeting over 11,000 total GPUs and $120 million in additional annual run-rate revenue by the end of 2026.
Key Details
- Dell Agreement: Buzz signed an agreement to deploy a 63-node cluster of liquid-cooled Dell PowerEdge XE9680L servers.
- Hardware Specifications: The deployment includes 504 latest-generation GPUs optimized for AI compute, delivered through Dell integrated rack scalable systems (IR5000 racks).
- Deployment Location: Delivery and installation will occur at the Bell AI fabric data centre.
- Bell Partnership: Operating agreements have been executed for the commencement of the first phase of the Buzz and Bell AI fabric deployment.
- Rankings: Buzz recently achieved bronze status in the semi-analysis ClusterMax rankings, surpassing publicly traded peers in the AI cloud sector.
- Future Capacity (2026):
- Buzz is procuring long-lead components for sites in Canada and Sweden, with go-live targeted for the second half of calendar 2026.
- Each Canadian and Swedish site, alongside the Bell AI fabric facility, will support 2,000 additional latest-generation GPUs.
- Total target fleet: Over 6,000 latest-generation GPUs for AI cloud by the end of 2026.
- Financial Projections:
- The projected expansion is expected to generate an additional $120 million in annual run-rate revenue.
- Operating margin is estimated at 80% after electrical and data centre costs.
- This increase is in addition to the company's current $20 million Annual Recurring Revenue (ARR).
- Total GPU Count: Combined with over 5,000 GPUs already in operation, the Buzz AI cloud will reach a total of over 11,000 GPUs by the end of 2026.
- Grand Falls Facility: The Hive 70-megawatt Tier I data centre in Grand Falls, N.B., sits on 32.5 acres of land and is positioned for upgrade to a Tier 3+ hyperscaler co-location facility, capable of supporting over 25,000 latest-generation GPUs based on reference architecture.
Notable Quotes