Digi Power X has $85M (U.S.) in liquidity at Oct. 31

DGX · Price
Executive Summary
- Digi Power X Inc. reported a significant strengthening of its balance sheet, with total liquidity (cash, crypto, and deposits) increasing from $29 million to approximately $85 million as of October 31, 2025.
- The company provided an operations update detailing its transition from cryptocurrency mining to AI infrastructure, including the production of ~25 BTC in October and the development of its NeoCloudz retail compute platform and ARMS 200 modular solution, both expected to launch in January 2026.
- Digi Power X outlined a phased AI infrastructure deployment roadmap targeting 55 MW of total capacity by Q4 2026, leveraging its existing 196.7 MW of available power across Alabama and New York sites.
Key Details
- Liquidity Position: Total liquidity (cash, BTC, ETH, and deposits) rose to ~$85 million as of Oct 31, 2025, up from $29 million on Sept 30, 2025.
- Bitcoin Holdings:
- Inventory increased from ~100 BTC to 112 BTC (a 12% increase) as of Oct 31, 2025.
- BTC price used for valuation: $109,600 (Oct 31) vs $113,300 (Sept 30).
- Value of BTC produced via self-mining and co-location agreements in October: ~$3.4 million.
- Miners produced ~25 BTC in October, valued at ~$2.7 million.
- Ethereum Holdings:
- Held ~1,000 ETH as of Oct 31, 2025, with a fair market value of ~$3.8 million.
- ETH is staked to generate an annualized return of ~3%.
- ETH price used for valuation: $3,800 (Oct 31) vs $4,160 (Sept 30).
- Capital Expenditures:
- Year-to-date capex: ~$8.6 million.
- October capex: ~$2.8 million, directed toward data centre infrastructure support equipment.
- NeoCloudz Platform:
- Retail compute platform expected to launch in January 2026.
- Built on Supermicro enterprise-grade backbone.
- Provides on-demand GPU compute access for developers, start-ups, and enterprises.
- Leverages Tier III infrastructure, liquid cooling, and low-latency networking.
- ARMS 200 Platform:
- AI-ready modular solution expected to begin implementation in January 2026.
- Designed for rapid, scalable AI compute infrastructure at operational sites.
- AI Infrastructure Deployment Roadmap:
- Q1 2026: 5 MW.
- Q2 2026: 15 MW.
- Q3 2026: 30 MW.
- Q4 2026: Total 55 MW (including 40 MW critical load capacity).
- Power Asset Availability:
- Alabama site: 55 MW.
- New York sites: 141.7 MW.
- Total available power today: 196.7 MW.
- North Carolina site: 200 MW (anticipated availability by 2028).
- 2027 Targets:
- Targeting total operational capacity of 195 MW.
- Targeting 140 MW of critical AI compute infrastructure.