ZAC 0.060 +0.0% ELE 21.18 −1.7% GHRT 0.750 +0.0% AEM 203.13 +0.1% JTWO 0.135 +0.0% EDR 10.63 −2.8% VMXX 0.750 +5.6% K 32.71 −1.5% AGI 40.13 −1.4% VGZ 2.40 +0.8% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% ZAC 0.060 +0.0% ELE 21.18 −1.7% GHRT 0.750 +0.0% AEM 203.13 +0.1% JTWO 0.135 +0.0% EDR 10.63 −2.8% VMXX 0.750 +5.6% K 32.71 −1.5% AGI 40.13 −1.4% VGZ 2.40 +0.8% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0%
Production / Operations

Aclara to build U.S. heavy rare-earths facility

ARA · Price

Executive Summary

  • Aclara Resources Inc. announced the decision to construct the first heavy rare-earths (HREE) separation facility in the United States, located in Louisiana.
  • The project aims to secure sustainable feed from two ionic clay deposits in Brazil (Carina) and Chile (Penco), with production expected to begin by mid-2028.
  • The initiative is part of Aclara's "mine-to-magnet" strategy, involving a $277-million investment and supported by approximately $46.4-million in Louisiana state tax incentives and grants.

Key Details

  • Facility Location & Investment: The separation facility will be built on an 82-acre LED-certified site at the Port of Vinton, Louisiana. Aclara will invest approximately $277-million (U.S.) for development.
  • Production Timeline: The facility is scheduled for completion in 2027, contingent on funding and offtake agreements. Secured sustainable feed from Brazil and Chile is expected by mid-2028.
  • Production Capacity: Upon full production, the facility is anticipated to produce:
    • 200 tonnes per year (tpy) of Dysprosium (Dy)
    • 30 tpy of Terbium (Tb)
    • 1,400 tpy of Neodymium-Praseodymium (NdPr)
    • This represents approximately 14% of China's official DyTb production.
  • Market Impact: Aclara anticipates supplying more than 75% of U.S. requirements for DyTb for electric vehicles by 2028.
  • Feed Sources: The facility will integrate with Aclara’s ionic clay deposits in Brazil (Carina project) and Chile (Penco module).
    • The Carina prefeasibility study (PFS) is scheduled for publication in early November 2025.
    • The feasibility study (FS) for Carina is expected in Q2 2026.
    • Significant progress has been made at the Goiania pilot plant in Brazil to enhance the purity of mixed rare-earth carbonate.
  • Technology & Partnerships:
    • Virginia Tech: Aclara is collaborating with Virginia Tech to validate its proprietary separation process via a pilot plant, expected to be fully operational by Q1 2026. This will provide ~1.5 years of feed-specific operational data before Louisiana production starts.
    • Hatch Ltd.: Retained to develop engineering for the Louisiana project and the Carina project to ensure coordination and cost-efficiencies.
    • VAC (VacuumSchmelze): Aclara has a strategic alliance with VAC, which is building a permanent magnet production facility in Sumter, South Carolina.
    • CAP Joint Venture: Aclara is advancing alloy-making capabilities through a joint venture with CAP to convert refined oxides into alloys for permanent magnets.
  • Louisiana Incentives: The State of Louisiana is providing an estimated $46.4-million (U.S.) in support, including:
    • Industrial Tax Exemption Program (ITEP): 80% ad valorem tax exemption for 5 years (renewable). Estimated value: $29.3-million.
    • High-Impact Jobs Program (HIP): Cash grants of 18-22% of wages for new jobs. Estimated value: $11.6-million.
    • Performance-based Infrastructure Grant: Reimbursement for utility/road improvements. Estimated value: $3.0-million.
    • LED FastStart: Employment recruitment and training services. Estimated value: $2.5-million.
  • Additional Plans: Aclara plans an additional investment to construct a metals and alloys plant on the Louisiana property to support the high-performance permanent magnet industry.

Notable Quotes

  • Ramon Barua, CEO: "We are pleased to announce that we have secured a premium site in Louisiana for our U.S. heavy rare-earth separation facility... Our project is unique in the Western world: with direct access to our ionic clay deposits, this will be the only fully integrated heavy rare-earth separation operation currently capable of producing material volumes of heavy rare earths at scale."
  • Hugh Broadhurst, COO: "This facility will become a cornerstone of critical minerals reindustrialization in the Western Hemisphere... The incentive package offered by the State of Louisiana underscores the state's commitment to attracting high-technology and sustainable manufacturing investments."
  • Governor Jeff Landry: "By choosing Louisiana for its first U.S. facility, Aclara is recognizing what we already know, our state is leading the next generation of energy and technology innovation."
Read the original news release →