Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.27 +0.5% Oil 86.53 +0.6% Palladium 1,030.00 +0.9% TIG 0.800 +0.0% RVG 0.715 −4.0% FNV 354.26 −2.4% FDY 4.30 −0.5% MAU 16.05 −3.2% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7% Gold 4,000.50 −0.7% Silver 52.00 +1.5% Copper 6.27 +0.5% Oil 86.53 +0.6% Palladium 1,030.00 +0.9% TIG 0.800 +0.0% RVG 0.715 −4.0% FNV 354.26 −2.4% FDY 4.30 −0.5% MAU 16.05 −3.2% VOXR 6.78 −0.6% TLO 7.04 −1.0% NICU 1.95 −5.8% VTEN 0.440 +0.0% AWM 0.025 +0.0% OR 50.79 −1.8% AUXX 5.30 −5.5% TNR 0.420 +40.0% ORCL 0.030 +0.0% ELD 47.71 −5.4% OPW 0.140 −6.7%
Other

Amex to prepare for power line work to Perron

AMX · Price

Executive Summary

  • Amex Exploration Inc. has awarded a mandate to contractor Moreau to handle planning, engineering, and regulatory permitting for a dedicated 25-kilovolt power line connecting Hydro-Quebec's Normetal substation to the Perron project in Valcanton.
  • The 6.5-kilometer line is targeted for commissioning in Q3 2026, providing a stable, renewable power source that will replace diesel generators and support bulk sampling and Phase 1 toll-milling operations.
  • Securing permanent grid power early is expected to improve cost visibility, operational reliability, and technical/economic parameters currently being evaluated in the Phase 1 feasibility study.

Key Details

  • Contractor: Moreau (Abitibi-based specialist in industrial electrical infrastructure)
  • Scope of Work: Preparatory work, planning, engineering, and regulatory permitting for the power line construction
  • Infrastructure Specs: 25-kilovolt medium-voltage line, approximately 6.5 km in length
  • Route: Hydro-Quebec Normetal substation to the Perron project site
  • Commissioning Timeline: Third quarter of 2026 (subject to permit approval)
  • Operational Use: Supports bulk sampling activities and projected Phase 1 toll-milling operations (currently in feasibility study)
  • Environmental & Economic Impact: Eliminates diesel generator dependence, lowers greenhouse gas emissions, reduces fuel-handling risks, improves site efficiency, and enhances overall project robustness and cost visibility
  • Technical Oversight: Reviewed and approved by Stephen Coates, PEng, independent qualified person under National Instrument 43-101

Notable Quotes

  • Victor Cantore, President & CEO: "Direct connection to Hydro-Quebec's grid is expected to be an important contributor to the technical and economic parameters being evaluated in the ongoing phase 1 feasibility work. Establishing permanent grid power early enhances cost visibility, operating reliability and overall project robustness."