GOLD 4163.10 −0.4% SILVER 57.36 +0.1% COPPER 6.59 +0.3% OIL 99.14 +0.1% PALLADIUM 1123.75 −0.4% WGX 4.83 −1.6% WCU 0.130 +8.3% SAGE 0.105 −4.5% BHS 0.055 +10.0% BARU 0.050 +11.1% REC 0.050 +0.0% NICN 0.130 +13.0% TRX 1.47 −2.6% VLC 0.240 +14.3% TIGR 0.660 +6.5% TUO 1.42 −0.7% SVG 0.125 +0.0% VCU 1.02 +0.0% MACK 3.27 +5.5% COSA 0.390 −1.3% WGLD 0.130 +0.0% GOLD 4163.10 −0.4% SILVER 57.36 +0.1% COPPER 6.59 +0.3% OIL 99.14 +0.1% PALLADIUM 1123.75 −0.4% WGX 4.83 −1.6% WCU 0.130 +8.3% SAGE 0.105 −4.5% BHS 0.055 +10.0% BARU 0.050 +11.1% REC 0.050 +0.0% NICN 0.130 +13.0% TRX 1.47 −2.6% VLC 0.240 +14.3% TIGR 0.660 +6.5% TUO 1.42 −0.7% SVG 0.125 +0.0% VCU 1.02 +0.0% MACK 3.27 +5.5% COSA 0.390 −1.3% WGLD 0.130 +0.0%
Regulatory

Earthworks Industries Inc. - CORTINA UPDATE

EWK · Price

Executive Summary

  • Earthworks Industries’ U.S. subsidiary, Cortina Integrated Waste Management Inc., filed a complaint challenging the IBIA’s order that sought to cancel its lease with the Kletsel Dehe Wintun Nation.
  • A stipulation was entered on October 16, 2025, vacating the hearing scheduled for October 27, 2025, and placing all summary‑judgment motions under submission pending future court action.
  • The delay is due to a lapse in U.S. Department of Justice appropriations; the parties will seek a new hearing date once federal funding is restored.

Key Details

  • Parties Involved: Cortina Integrated Waste Management Inc. (wholly owned subsidiary of Earthworks Industries) vs. United States Department of the Interior’s Board of Indian Appeals and the Kletsel Dehe Wintun Nation.
  • Legal Issue: Challenge to the IBIA order that purportedly cancels the federally approved lease for the Cortina Rancheria site in California.
  • Stipulation Date: October 16, 2025; approved by the U.S. District Court for the Eastern District of California.
  • Effect of Stipulation: Hearing set for October 27, 2025, is vacated; Plaintiff’s Motion for Summary Judgment and Defendant‑Intervenor’s Cross‑Motions are placed under submission.
  • Reason for Delay: Federal appropriations that fund the U.S. Department of Justice expired on September 30, 2025; without a continuing resolution, DOJ attorneys cannot work on civil cases.
  • Future Proceedings: Court retains authority to reopen the matter for additional briefs or oral arguments; parties will request any rescheduled hearing be set as soon as funding permits.
  • Company Outlook: Earthworks Industries anticipates a successful affirmation of the lease’s validity and enforceability by the court.

Notable Quotes

“The Company looks forward to a successful affirmation by the Court of the validity and enforceability of the lease at Cortina.” – David Atkinson, President/CEO, Earthworks Industries Inc.

Read the original news release →