GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
M&A / Property Routine +

Abitibi Metals Secures 100% Ownership of the B26 Deposit and Establishes a District Scale Consolidation Platform Across the Selbaie Camp

AMQ · Price

Executive Summary

  • Abitibi Metals Corp. has entered into a definitive agreement to acquire SOQUEM Inc.'s remaining 20% interest in the B26 Polymetallic Deposit, securing 100% ownership of its flagship Quebec asset.
  • The transaction features a ~C$7M initial consideration structure with milestone payments tied to feasibility and construction stages, alongside a 1% NSR royalty retained by SOQUEM.
  • The agreement includes a 10-year Right of First Refusal on SOQUEM's Wagosic and Carheil properties, establishing a strategic pathway for district-scale consolidation in the Selbaie Mining Camp.

Key Details

  • Transaction Type: Acquisition of remaining 20% joint venture interest in the B26 Polymetallic Deposit from SOQUEM Inc.
  • Initial Consideration (~C$7M):
  • Upon closing: C$5M in cash (payable within 90 days, reduced by 20% of SOQUEM's attributable exploration expenditures) + C$2M in Abitibi Metals shares.
  • Milestone 1 (Feasibility study or ≤3 years post-closing): C$6M payable 50% cash / 50% shares.
  • Milestone 2 (Construction decision or ≤5 years post-closing): C$6M payable 50% cash / 50% shares.
  • Royalty Terms: SOQUEM retains a 1% Net Smelter Return (NSR) royalty on B26; the existing 2023 JV royalty terminates at closing.
  • Default Provisions: Failure to meet milestones triggers additional NSR (1% at feasibility, 0.5% at construction) and JV re-formation with equity reversion (12% at feasibility, 6% at construction). Abitibi retains the right to repurchase any additional NSR for C$2M.
  • Resource Estimate: 2026 updated resource comprises 13.0M tonnes Indicated at 2.1% CuEq and 12.4M tonnes Inferred at 2.2% CuEq, totaling 25.3M tonnes (124% growth since the Company's initial option in 2023).
  • Consolidation Rights: 10-year Right of First Refusal (ROFR) on SOQUEM's 100% owned Wagosic and Carheil properties.
  • Collaboration Framework: A joint technical committee will be established to advance B26 and Wagosic concurrently, beginning with blended metallurgical test work to evaluate combined development scenarios.
  • Project Context: B26 is located 7 km southeast of the formerly producing Selbaie Mine in northwestern Quebec's Selbaie Mining Camp.

Notable Quotes

  • "Securing 100% ownership of B26 represents a transformative milestone for Abitibi Metals... With full ownership now secured, we have complete control over the future direction of the project and the ability to maximize value for our shareholders." – Jon Deluce, President and CEO