Gold 4,077.40 +0.1% Silver 54.55 +0.1% Copper 6.66 +0.1% Oil 99.88 −0.0% Palladium 1,035.75 +0.4% GBU 0.085 +13.3% GAMA 0.060 +0.0% QGR 0.190 +2.7% AVU 0.020 +0.0% GCN 0.025 +0.0% PML 1.37 +5.4% NVO 0.055 +0.0% OSM 0.030 +20.0% GSKR 2.72 +4.6% GPG 0.265 −1.9% UCU 1.95 +2.6% PPX 0.240 +4.3% SXL 0.055 +0.0% ONAU 0.540 +8.0% TMQ 3.15 +10.9% MOON 6.10 +9.9% Gold 4,077.40 +0.1% Silver 54.55 +0.1% Copper 6.66 +0.1% Oil 99.88 −0.0% Palladium 1,035.75 +0.4% GBU 0.085 +13.3% GAMA 0.060 +0.0% QGR 0.190 +2.7% AVU 0.020 +0.0% GCN 0.025 +0.0% PML 1.37 +5.4% NVO 0.055 +0.0% OSM 0.030 +20.0% GSKR 2.72 +4.6% GPG 0.265 −1.9% UCU 1.95 +2.6% PPX 0.240 +4.3% SXL 0.055 +0.0% ONAU 0.540 +8.0% TMQ 3.15 +10.9% MOON 6.10 +9.9%
Production / Operations Routine +

South Star Announces Santa Cruz Operational Update; First Shipment of Graphite Shipped

STS · Price

Executive Summary

  • South Star Battery Metals announced May operational results and continued ramp-up at its Santa Cruz graphite plant in Brazil, marking a transition to a continuous 24-hour operational cycle.
  • The company reported substantial throughput increases, processing approximately 5,136 tonnes of ROM ore since restart and producing ~25 tonnes of graphite concentrate with grades up to 97% carbon.
  • Near-term objectives focus on stabilizing filtration, optimizing the grinding circuit, and scaling production to meet the technical report target of 5,000 tonnes per annum (tpa) of graphite concentrate.

Key Details

  • Operational Milestones: Commissioning completed in the first week of May; plant transitioned from a 9-hour single shift to a continuous 24-hour operational cycle; newly hired employees completed training and assumed permanent production roles; first graphite concentrate shipment prepared.
  • Throughput Metrics: April 2026 ROM feed: 1,337.5 tonnes; May 2026 ROM feed: 3,798.5 tonnes; Total ROM ore processed since restart: ~5,136 tonnes; Total graphite concentrate produced: ~25 tonnes.
  • Product Quality: Graphite concentrate grades achieved up to 97% carbon during the first month of startup.
  • Process Optimization: Quality control and process engineering teams now generating reliable operating data across the full process circuit (feed, process streams, final products, tailings); modifications to the plant feed and front-end processing successfully stabilized the downstream process.
  • Near-Term Objectives: Fine-tune filter press to determine optimal filter cloth for stable filtration; install already-purchased balls and rods in the grinding circuit to improve graphite liberation from gangue; adjust and monitor plant to reach 5,000 tonnes of graphite concentrate production per year (Years 1-3 goal per technical report filed with ANM, the Brazilian mining regulatory agency).
  • Management: Tiago Cunha serves as Interim CEO; Rogerio Barcellos serves as COO.

Notable Quotes

  • Tiago Cunha, Interim CEO: “Our team, led by COO Rogerio Barcellos, has delivered an exceptional 2 months of operational results. The plant is being monitored regularly and consistently in order to attain a production capacity of 5,000 tpa of graphite concentrate. The early indications show positive results thus far.”