Asante Gold Corporation (ASE) released results from reverse circulation and diamond drilling in the "Main Pit Bridge" area at its Bibiani mine. This zone lies between the operating Main Pit and Cut 5 and is part of an 8,000-meter programme covering approximately 350 meters of strike to a depth of 150 meters. All intercepts are reported as downhole lengths using a 0.36 g/t Au cutoff, a maximum 3-meter internal waste allowance, and a minimum 2-meter interval.
Key intercepts include:
- MGRC26-763: 60 m at 3.13 g/t Au from 103 m; plus 13 m at 5.59 g/t from 85 m; plus 10 m at 1.36 g/t from 71 m
- MGRC26-758: 34.0 m at 3.59 g/t Au from 140 m
- MGRC26-762B: 25 m at 4.95 g/t Au from 119 m; plus 9 m at 1.57 g/t from 104 m
- MGRC26-743: 40 m at 2.76 g/t Au from 65 m
- MGRC26-741: 48 m at 2.12 g/t Au from 42 m, ended in mineralization at 90 m due to rig malfunction, including 24 m at 2.77 g/t from 53 m and 7 m at 5.26 g/t from 69 m
- MGRC26-747: 16 m at 5.25 g/t Au from 80 m and 17 m at 4.36 g/t Au from 119 m
- MGRC26-765: 6 m at 62.48 g/t Au from 136 m
- MGRC26-755: 21 m at 2.16 g/t
- MGRC26-769: 24 m at 1.89 g/t
- MGRC26-759: 22 m at 1.55 g/t
- MGRC26-764: 18 m at 1.46 g/t
- MGRC26-756: no significant intercept
The drilling aims to upgrade Inferred resources to Indicated within the Bridge area and to test whether material currently modeled as Main Pit underground can be mined as an open pit. This approach could defer underground development capital expenditure planned for 2027-2028. The company stated that no estimate of additional tonnes, grade, mine life, or deferred capital expenditure has been established at this stage. Historical Cut 5 intercepts, such as 42.8 m at 6.30 g/t from 345 m in RCD-04-600, are included in the existing 31-Dec-2025 resource database rather than representing new assays.
Six of the seven headline intercepts—MGRC26-763, MGRC26-741, MGRC26-762B, MGRC26-743, the 13 m at 5.59 g/t interval, and the 6 m at 62.48 g/t interval—were already published in the 13-Nov-2026 Q3 results release. The content released on 16-Nov consists of the full Appendix 1 table, collar and QA-QC details, and data for two holes: MGRC26-758 and MGRC26-747.
Asante Gold Corporation (ASE) released drill results that confirm grade and continuity at or modestly above the 2.08 g/t resource grade and the 2.00 g/t reserve grade. The company already hosts Indicated and Inferred material inside the existing 2.06 moz Bibiani M&I inventory, and these new holes serve to validate the existing resource definition rather than significantly alter the mine plan. The release advances a mine-plan review that could convert underground ounces to open-pit ounces and defer underground capital, but it does not, on its own, change reserves, mine life, or net asset value.
The drill intercepts include the following results:
- MGDD25-550: 29.1 m at 1.17 g/t, ~34 g·m
- RCD-04-600: 42.8 m at 6.30 g/t, ~270 g·m (from 345 m depth)
The new data points, with headline gram-metres of 188, 124, and 122, exceed the best previously reported Bibiani Main Pit intercept and sit close to historical Cut 5 results.
The equity is currently trading at its 52-week low of C$0.41, down 82% from C$2.33. The stock fell 34% in a single session on 13-Nov on the Q3 print, the same session in which six of these intercepts first appeared. The market is currently pricing a funding cliff rather than the drilling results. The dominant price driver is a US$100 million funding requirement due 30-Nov-2026, which is fourteen days after this release, alongside a $309.7 million working capital deficiency and an explicit going-concern qualification.
Asante Gold Corporation has a C$374 million market cap against 4.6 moz M&I and 2.83 moz reserves. A few hundred thousand ounces of potential open-pit conversion at ~2-3 g/t, plus capital deferral of unspecified size in 2027-2028, is incremental to that equation. A step-change would require a quantified mine-plan revision, which is expected in a future release.
Asante Gold Corporation (ASE) is a Ghana-focused gold producer, developer, and explorer listed on the TSXV, the Ghana Stock Exchange, and OTCQX. The company holds over 80 km of strike on the Sefwi-Bibiani belt and operates three primary assets: Bibiani, Chirano, and the Kubi gold project.
The Bibiani operation, which is operator-controlled, features an open-pit mine with a refurbished plant and a new sulphide treatment plant with a nameplate capacity of approximately 4.0 Mt/y, alongside an underground project. The asset holds 1.53 moz in reserves (23.75 Mt at 2.00 g/t), 2.06 moz in Measured and Indicated resources (30.83 Mt at 2.08 g/t), and 965 koz in Inferred resources, supporting a nine-year life of mine. Drilling in 2024-2025 totaled approximately 43,000 m, and the Main Pit is open at depth to at least 1,400 m.
Asante Gold acquired Chirano in August 2022. This open-pit and underground asset comprises multiple deposits, including Obra, Sariehu, Aboduabo, Tano, and Akoti. Chirano holds 1.30 moz in reserves (23.69 Mt at 1.71 g/t), 2.53 moz in Measured and Indicated resources (40.01 Mt at 1.96 g/t), and 830 koz in Inferred resources, with a seven-year life of mine. The asset generated US$112.8 M in gross profit for the nine months ended 2026. The Kubi gold project, located on the Ashanti belt, remains in an earlier stage of development.
Consolidated as of December 31, 2025, Asante Gold reported 4.6 moz in Measured and Indicated resources, 1.8 moz in Inferred resources, and 2.83 moz in reserves.
According to the November 13, 2026, Q3 filing, the company produced 165,594 oz eq in the nine months ended 2026, a 41% increase year-over-year. Revenue for the period was US$756.7 M, with Adjusted EBITDA of US$194.8 M. Consolidated all-in sustaining costs (AISC) stood at US$4,308/oz. The company reported a net loss of US$84.4 M, cash holdings of US$64.0 M, and total debt of US$301.3 M. Total equity was US$60.9 M, representing a book value of approximately US$0.07 per share. The company reported a working capital deficiency of US$309.7 M and disclosed a going-concern material uncertainty. 2026 guidance has been withdrawn. A "buybacks" line item of US$132.8 M appears in the nine-month cash-flow statement without explanation in the provided materials; given the liquidity position, this cannot be assumed to be equity repurchases and should be verified in the filing.