1911 Gold Advances True North Toward 2027 Production with Start of Underground Development and Test Mining Preparation
1911 Gold Commences Underground Development at True North, De-risking 2027 Restart Plan

Executive Summary
- 1911 Gold has commenced underground drift development on Level 16 of the True North Mine in Manitoba.
- Development targets include L10 and Hinge zones to prepare stopes for extraction and bulk sample programs.
- An underground development contract was awarded with mobilization expected in June 2026.
- Equipment arrivals are scheduled: three 2-yard scoops in June 2026, a single-boom jumbo in July 2026.
- Preliminary mine plan estimates 3,551 total meters of new development (2,056 m for Hinge, 1,495 m for L10).
- Infrastructure scope includes ramp development, sill drives, and essential infrastructure upgrades.
- Level 26 access was re-established in April 2026 to support ore movement and loading pocket operations.
- Test mining activities are planned for later this year (H2 2026) with commercial production targeted for 2027.
Material Impact
- The news confirms execution of the timeline established in the February 2026 PEA, which projected test mining in H2 2026 and production in 2027.
- Progress is on schedule; therefore, the information is not unexpected by the market following the PEA release.
- The commencement of underground development de-risks the project technically but does not alter the fundamental economic thesis established previously.
- No new strategic investors or major resource upgrades are announced in this specific release compared to historical drill results.
- Given the prior "Material - Positive" ratings for the PEA and Credit Facility, this operational update is incremental progress rather than a paradigm shift.
- The market has likely priced in the 2027 restart potential since February; thus, the immediate price impact is expected to be muted relative to previous catalysts.
AUMB · Price
Company Overview
- Company: 1911 Gold Corporation (TSX-V: AUMB).
- Flagship Project: True North Gold Project in the Rice Lake Greenstone Belt, Manitoba, Canada.
- Project Status: Advanced Development stage; Preliminary Economic Assessment (PEA) completed March 2026.
- Mine Type: Underground long-hole open stope mining utilizing existing infrastructure.
- Production Guidance: Targeting steady-state production of ~58,114 oz Au/year over an 11-year mine life starting in 2027.
- Infrastructure: Existing shafts (A Shaft, Hinge), processing plant (1,300 t/d), and tailings management facility are fully permitted with a replacement value >$400 million.