ELD 38.99 −0.4% WRN 3.01 +1.4% ELBM 0.720 +1.4% GAMA 0.080 +0.0% GRDM 0.095 +5.6% URC 3.89 −1.0% HMMC 5.62 +0.0% KNOX 0.270 +0.0% TRO 0.135 −3.6% PX 0.115 −8.0% SDR 0.145 +45.0% SWA 0.035 +0.0% FNV 281.28 −0.0% GGA 4.42 −25.7% NICU 2.23 +0.5% KAPA 0.155 +3.3% ELD 38.99 −0.4% WRN 3.01 +1.4% ELBM 0.720 +1.4% GAMA 0.080 +0.0% GRDM 0.095 +5.6% URC 3.89 −1.0% HMMC 5.62 +0.0% KNOX 0.270 +0.0% TRO 0.135 −3.6% PX 0.115 −8.0% SDR 0.145 +45.0% SWA 0.035 +0.0% FNV 281.28 −0.0% GGA 4.42 −25.7% NICU 2.23 +0.5% KAPA 0.155 +3.3%
Production / Operations

PowerBank Announces Safe Harbor of 15 Distributed Solar and Energy Storage Projects in New York State

SUNN · Price

Executive Summary

  • PowerBank Corp. announced execution of equipment procurement agreements for 15 late‑stage distributed solar and energy storage projects in New York State, totaling ~67 MW DC of solar and 11 MWh of storage.
  • The procurements are intended to “safe harbor” the projects, preserving eligibility for U.S. federal Investment Tax Credits (ITC) valued at an estimated US$65 million; total construction value is estimated at US$168 million.
  • Physical work on the procured equipment is expected to be completed by Dec 31 2025, meeting the IRS Physical Work Test deadline of July 4 2026 under the One Big Beautiful Bill Act.

Key Details

  • Projects: 15 distributed solar + energy storage projects across New York State.
  • Capacity: ~67 MW DC solar; ~11 MWh battery storage.
  • Construction Value: Approximately US$168 million for the portfolio.
  • Tax Credit Estimate: US$65 million in federal Investment Tax Credits (30% ITC plus potential bonus adders).
  • Procurement Scope: Major equipment order of transformers secured from Tier‑1 suppliers; subject to permits and financing.
  • Safe Harbor Timeline: Physical work on procured equipment expected to be completed by 31 Dec 2025, satisfying IRS Physical Work Test before the 4 Jul 2026 deadline.
  • Ownership Option: PowerBank may retain ownership of some or all projects as an Independent Power Producer; will deliver full EPC scope regardless of eventual ownership.
  • Commercial Operation: Anticipated over several years after receipt of permits, interconnection approvals, and financing.
  • Strategic Context: Projects support New York’s goal of 10 GW distributed solar & 6 GW storage by 2030; align with state’s leading community‑solar capacity.

Notable Quotes

(No direct CEO/President quotes were provided in the release.)