Gold 4,079.60 −0.8% Silver 51.94 −0.8% Copper 6.24 −0.5% Oil 90.83 +0.3% Palladium 1,017.10 −2.6% KRN 0.260 −7.1% GSKR 2.84 +5.6% ADE 0.125 +4.2% NRM 0.055 +0.0% BBB 0.520 −1.9% LGD 2.09 +1.9% DEC 0.110 +0.0% LCE 0.200 +0.0% NILI 0.515 −1.0% CDE 21.85 +6.7% CAN 0.045 +0.0% LORD 0.100 +0.0% HBM 29.49 +2.3% ELEF 0.265 +120.8% MUN 0.300 +0.0% SAGA 0.400 +6.7% Gold 4,079.60 −0.8% Silver 51.94 −0.8% Copper 6.24 −0.5% Oil 90.83 +0.3% Palladium 1,017.10 −2.6% KRN 0.260 −7.1% GSKR 2.84 +5.6% ADE 0.125 +4.2% NRM 0.055 +0.0% BBB 0.520 −1.9% LGD 2.09 +1.9% DEC 0.110 +0.0% LCE 0.200 +0.0% NILI 0.515 −1.0% CDE 21.85 +6.7% CAN 0.045 +0.0% LORD 0.100 +0.0% HBM 29.49 +2.3% ELEF 0.265 +120.8% MUN 0.300 +0.0% SAGA 0.400 +6.7%
Drill Results

Bunker Hill on Track for June Restart of Operations

Bunker Hill Confirms June Restart Path with Incremental Exploration Upside

Executive Summary
  • The most recent release dated May 4, 2026, confirms that Bunker Hill Mining Corp. remains on track for a mine restart in June 2026.
  • Approximately 93% of pre-production activities are now complete, including underground development and infrastructure readiness.
  • Exploration drilling (BHE26-01) at the "Cate-Eight" target identified high-grade silver and lead intercepts near existing underground infrastructure.
  • Specific intercepts include 2.3 ft at 11.1 oz/ton silver and 28.4% lead, consistent with broader vein zones.
  • Management states these results validate geological work underpinning the mine plan and could potentially increase total silver quantity in the near-term production plan.
Material Impact
  • The news is largely confirmatory regarding the June 2026 restart timeline, which has been consistently communicated since January 2026 (H1 2026 target) through April 2026 updates.
  • Exploration results are described as "consistent with our expectations," suggesting they do not represent a significant surprise or upside deviation that would materially alter valuation models immediately.
  • The finding of new veins near infrastructure is positive for operational flexibility but does not constitute a discovery of a new mine-scale resource at this stage.
  • Given the consistent messaging on restart progress over the last four months, the market likely has priced in the June timeline; therefore, this update is incremental rather than transformative.
  • The rating reflects Routine - Positive status as it validates execution without introducing unexpected catalysts or risks that would shift the investment thesis fundamentally.
BNKR · Price
Company Overview
  • Company: Bunker Hill Mining Corp. trades on TSX under ticker BNKR following graduation from TSX Venture Exchange in March 2026.
  • Flagship Project: The historic Bunker Hill Mine located in the Coeur d’Alene Mining District, Idaho, USA.
  • Project Status: Underground restart development targeting commercial production in H1 2026 (specifically June).
  • Mine Type: Mechanized underground mining using long-hole open stoping with paste backfill to reduce surface tailings footprint.
  • Production Target: Throughput expansion to 2,500 tpd supported by US EXIM financing plans for future growth ("Bunker Hill 2.0").
  • Revenue Mix: Projected 50% silver / 50% base metals (zinc/lead) revenue mix due to recent metal price strength.
Read the original news release →