Northwire Canada EditionThursday, July 23, 2026
Northwire
TECK 83.27 +3.2% FVI 11.89 −1.7% SUM 1.31 −1.5% RSMX 0.105 −4.5% STW 0.105 +5.0% PAT 0.250 +0.0% CCM 0.530 +1.9% SGN 0.250 −2.0% CNC 1.48 +0.7% PHNM 0.340 +4.6% LIO 0.160 +0.0% RIO 2.68 −3.9% KG 0.160 +3.2% GEN 0.065 +0.0% ECU 1.64 +8.6% ALTA 0.170 −2.9% TECK 83.27 +3.2% FVI 11.89 −1.7% SUM 1.31 −1.5% RSMX 0.105 −4.5% STW 0.105 +5.0% PAT 0.250 +0.0% CCM 0.530 +1.9% SGN 0.250 −2.0% CNC 1.48 +0.7% PHNM 0.340 +4.6% LIO 0.160 +0.0% RIO 2.68 −3.9% KG 0.160 +3.2% GEN 0.065 +0.0% ECU 1.64 +8.6% ALTA 0.170 −2.9%
Drill Results

Auriginal Identifies Fresh Mineralization Targets at Roger Project Through 3D Modeling, Indicating Resource Upgrade Potential

AUME · Price

Executive Summary

  • Auriginal Mining released a preliminary 3‑D model of the Roger Project that identifies new VMS‑type targets and suggests the historic Cu‑Au mineralization may extend ≥200 m to the NE and at depth below 350 m.
  • The model highlights a volcanic dome/cryptodome core with strong geophysical anomalies on its SW and NE flanks, supporting a Cu‑Zn‑Au‑Ag VMS system analogous to Agnico Eagle’s LaRonde Mine.
  • Based on these insights, the company revised its upcoming diamond drill program (8 holes, total 5 154 m) slated to start in early March 2026 to test depth continuity and newly identified targets.

Key Details

  • 3‑D Model Findings
  • Mineralization appears truncated NE by a NNW‑striking fault; displacement of alteration envelope suggests up‑dip continuation of porphyry Cu‑Au mineralization ≥200 m east of the fault.
  • Historical drilling validation shows no depth limit to ~350 m, indicating potential for deeper extensions.
  • Thickest zone aligns with the core of a volcanic dome/cryptodome; strongest BHEM (Borehole EM) response on SW and NE flanks.
  • Geophysical results corroborate VMS interpretation (Cu‑Zn‑Au‑Ag).

  • Comparative Geology

  • Structural and mineralogical similarities drawn to the LaRonde Mine (Agnico Eagle), reinforcing a high‑grade VMS prospectivity.

  • Revised Diamond Drill Program (Table 1)

Hole Easting Northing Elevation (m) Azimuth Dip (°) Extension (m) Target Depth (m) Revised Final Depth (m)
2026‑001 542 678.7 5 534 716 378.71 153 –65 80 527 667
2026‑002 542 443.6 5 534 629 378.45 153 –65 75 516 650
2026‑003 542 222.3 5 534 514 379.13 153 –65 50 515 622
2026‑004 541 967 5 534 466 380.68 153 –65 100 524 687
2026‑005 541 750.9 5 534 329 379.90 153 –65 60 527 646
2026‑006 541 551 5 534 248 375.34 160 –65 60 525 644
2026‑007 541 332.8 5 534 128 374.91 160 –65 40 523 619
2026‑008 541 096.9 5 534 043 373.52 160 –65 40 523 619
  • Total Planned Drilling Depth: 5 154 m (revised).

  • Planned Start Date: Early March 2026.

  • Qualified Person: Charles Beaudry, P.Geo (1202) and géo. (311), NI 43‑101 qualified.

Notable Quotes

“Our 3‑D visualization work has revealed significant new targets that could substantially expand the historic Cu‑Au resource at Roger, and we have adjusted our drill program accordingly to test these high‑potential zones.” – Peter Cashin, CEO, Auriginal Mining Corp.

Read the original news release →

More from Auriginal Mining Corp.