Northwire Canada EditionTuesday, August 4, 2026
Northwire
FAIR 0.050 +0.0% ELR 0.345 +0.0% LMCU 8.77 +0.0% MKA 0.720 +0.0% SCD 0.160 +0.0% TECK 84.36 +0.0% SAGA 0.435 +0.0% BZ 3.16 +0.0% FFM 1.68 +0.0% LOD 0.335 +0.0% AEC 5.52 +0.0% ORV 1.88 +0.0% MCM 0.300 +0.0% GAMA 0.075 +0.0% AIR 0.050 +0.0% LUN 34.71 +0.0% FAIR 0.050 +0.0% ELR 0.345 +0.0% LMCU 8.77 +0.0% MKA 0.720 +0.0% SCD 0.160 +0.0% TECK 84.36 +0.0% SAGA 0.435 +0.0% BZ 3.16 +0.0% FFM 1.68 +0.0% LOD 0.335 +0.0% AEC 5.52 +0.0% ORV 1.88 +0.0% MCM 0.300 +0.0% GAMA 0.075 +0.0% AIR 0.050 +0.0% LUN 34.71 +0.0%
Resource Estimate

Gold X2 Mining Delivers Preliminary Economic Assessment and Updated Mineral Resource Estimate for the Moss Gold Project

AUXX · Price

Executive Summary

  • Gold X2 Mining released a PEA for the Moss Gold Project showing after‑tax NPV5% of $2.232 bn (base case), IRR 22.1 % and a 3.2‑year payback at a gold price of US$2,750/oz.
  • Updated MRE reports indicated resources of 2.125 Moz Au (Indicated) and 3.910 Moz Au (Inferred) with accompanying silver grades, representing a ~73 % increase in Indicated ounces versus the prior estimate.
  • Capital requirements are projected at C$2.001 bn initial capex plus C$839 M sustaining capex; operating costs are low‑quartile (AISC US$1,188/oz Au).

Key Details

  • PEA Economic Highlights (Base Case – US$2,750/oz Au):
  • After‑tax NPV5%: C$2.232 bn
  • IRR: 22.1 %
  • Payback period: 3.2 years
  • Average annual payable gold production: ~265,000 oz; silver: ~374,000 oz (13.2‑year mine life)
  • After‑tax free cash flow over LOM: C$4.035 bn

  • PEA Economic Highlights (Long‑Term Consensus – US$3,137/oz Au):

  • After‑tax NPV5%: C$3.152 bn; IRR 28.1 %; Payback 2.5 years

  • PEA Economic Highlights (Spot Gold – US$4,600/oz Au):

  • After‑tax NPV5%: C$6.578 bn; IRR 48.6 %; Payback 1.0 year

  • Operating Cost Summary:

  • Mining cost: C$18.88/t milled (US$14.09)
  • Processing cost: C$12.29/t milled (US$9.17)
  • G&A cost: C$3.16/t milled (US$2.36)
  • Total site cost: C$34.33/t milled (US$25.62)
  • Cash Cost: US$999/oz Au; AISC: US$1,188/oz Au

  • Capital Expenditure:

  • Initial capex: C$2.001 bn (US$1.493 bn) – includes $303 M contingency
  • Sustaining capex: C$839 M (US$626 M)
  • Closure & monitoring: C$49 M; Working capital during construction: C$26 M; Salvage value: C$32 M

  • Mineral Resource Estimate (effective Jan 16 2026):

  • Indicated: 2.125 Moz Au at 1.03 g/t; 3.160 Moz Ag at 1.53 g/t within 64.3 Mt
  • Inferred: 3.910 Moz Au at 0.97 g/t; 6.273 Moz Ag at 1.55 g/t within 125.9 Mt
  • 73 % increase in Indicated ounces versus prior estimate, driven by new structural modeling and 2025 drilling

  • Mine Plan & Production Profile:

  • Open‑pit truck‑and‑shovel operation; 30,000 t/d processing plant
  • Total mill feed: 138,982 kt at 0.88 g/t Au; waste rock 668,255 kt; overburden 72,208 kt (strip ratio 5.3:1)
  • Expected total gold production: ~3.6 Moz; silver: ~4.5 Moz over LOM

  • Metallurgical Recovery:

  • Gold recovery: 91.7 % (consistent with PEA)
  • Silver recovery: 82.8 %

  • Power & Infrastructure:

  • Planned 40 MW power supply via a 12 km spur from Hydro One line; expected cost C$0.11/kWh

  • Royalties & Net Profit Interest:

  • NSR royalty average 0.11 % LOM
  • Net profit interest: 7.25 % after costs (capped at 5 % of sales)

  • Forward‑Looking Plans:

  • Feasibility Study targeted for H2 2027; environmental assessment and permitting work ongoing.
  • Exploration programs planned to expand resources adjacent to the pit, increase depth potential, and improve grade control.

Notable Quotes

“The Moss deposit MRE and PEA represents a major milestone… we have clearly demonstrated the potential for the Moss Deposit to be a top ten gold producer in Canada.” – Michael Henrichsen, CEO


All amounts are in Canadian dollars unless otherwise noted.

Read the original news release →

More from Gold X2 Mining Inc.