Northwire Canada EditionWednesday, July 29, 2026
Northwire
NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0%
Production / Operations

Nord Precious Metals completes radar survey at Castle

NTH · Price

Executive Summary

  • Nord Precious Metals completed a four‑day deep ground penetrating radar (DGPR) orientation survey at the Castle property to map historic underground workings down to ~100 m depth.
  • The survey aims to identify mineralized stopes, fractures, vein extensions, and lithologic contacts that will guide upcoming sonic drilling of historic tailings and future back‑fill operations.
  • Results will be delivered by Earth Scan Technologies as maps, vertical sections, and a 3‑D model; the data may support expansion of the survey area pending findings.

Key Details

  • Survey Scope: DGPR conducted with Earth Scan Technologies; penetrates to 200 m, targeting upper four levels (21 m & 48 m depths) of historic mine openings at Castle.
  • Objectives:
  • Distinguish mineral‑filled versus empty stopes.
  • Map fractures and potential new vein structures or extensions.
  • Delineate Nipissing diabase contact, source of high‑grade silver mineralization.
  • Data Deliverables: Final report with maps, vertical sections, interpretations of stope/vein characteristics, and a 3‑D model (contingent on data density).
  • Integration with Future Work: Survey results will be combined with an upcoming sonic drill program on Miller Creek tailings to assess recovery of silver and critical metals.
  • Remediation Plan: Using Ontario’s new recovery permit, Nord intends to process historic tailings into a high‑grade silver gravity concentrate containing critical metal sulfides, then backfill empty stopes with cemented tailings for ground stabilization.
  • Survey Duration: Completed in four days on site; potential expansion if depth detail and vein identification warrant further work.
  • Qualified Person: Frank J. Basa, P.Eng., (Peo), director of Nord Precious Metals, approved the technical information per NI 43‑101.

Notable Quotes

(No direct quotes were provided in the release.)

Read the original news release →

More from Nord Precious Metals Mining Inc.