Northwire Canada EditionThursday, July 30, 2026
Northwire
FCI 0.330 +0.0% SGQ 0.350 +0.0% TECK 85.57 +5.8% BIG 0.750 +27.1% PTU 0.320 −3.0% GZD 0.080 −11.1% AFM 1.45 +1.4% VCT 0.065 +8.3% BEM 0.060 −7.7% NMI 0.195 +0.0% VLD 0.540 +0.0% BOL 0.080 +6.7% EDCU 0.430 −2.3% SYH 0.380 +2.7% TECT 2.10 +2.4% NAU 1.49 −0.7% FCI 0.330 +0.0% SGQ 0.350 +0.0% TECK 85.57 +5.8% BIG 0.750 +27.1% PTU 0.320 −3.0% GZD 0.080 −11.1% AFM 1.45 +1.4% VCT 0.065 +8.3% BEM 0.060 −7.7% NMI 0.195 +0.0% VLD 0.540 +0.0% BOL 0.080 +6.7% EDCU 0.430 −2.3% SYH 0.380 +2.7% TECT 2.10 +2.4% NAU 1.49 −0.7%
Earnings

Eldorado Gold Reports Strong Q2 2025 Financial and Operational Results; Maintains 2025 Production Guidance; Skouries On Track for Q1 2026

ELD · Price

Executive Summary

  • Eldorado Gold reported Q2 2025 gold production of 133,769 oz, revenue of $451.7 M, and net earnings attributable to shareholders of $139.0 M ($0.68 per share), a material improvement over the prior year.
  • Total cash costs rose to $1,064/oz and AISC to $1,520/oz, driven by higher royalty rates in Turkey and Greece; the company reaffirmed its 2025 production guidance of 460‑500 k oz and expects full‑year cash‑costs/AISC at the high end of current ranges.
  • Significant project updates: Skouries capital spend reached $117.0 M in Q2, construction is ~70% complete for Phase 2, first copper‑gold concentrate production targeted for Q1 2026, and new zero‑cost gold collars were entered into covering 28 k oz (July 2027–Dec 2027).

Key Details

  • Production & Sales
  • Gold produced: 133,769 oz (up from 122,319 oz YoY) – driven by accelerated inventory drawdown at Kisladag and higher grade/throughput at Lamaque.
  • Gold sold: 131,489 oz at an average realized price of $3,270/oz.

  • Cost Metrics

  • Production costs: $162.2 M.
  • Total cash costs: $1,064/oz (up from $940/oz YoY).
  • All‑in sustaining cost (AISC): $1,520/oz (up from $1,331/oz YoY).

  • Capital Expenditures

  • Total capex Q2 2025: $240.9 M, including $117.0 M project capital at Skouries and $27.1 M accelerated operational capital.
  • Growth capital for operating mines: $47.3 M (mainly waste stripping & heap leach pad at Kisladag; development at Lamaque).

  • Financial Performance

  • Revenue: $451.7 M (vs. $297.1 M Q2 2024).
  • Net cash from operating activities: $158.2 M.
  • Adjusted EBITDA: $211.8 M; Adjusted net earnings: $90.1 M ($0.44/share).
  • Free cash flow (excluding Skouries): +$61.5 M; overall free cash flow negative ($61.6 M) due to growth capex.
  • Cash & equivalents at June 30 2025: $1,078.6 M, up $221.8 M YoY.

  • Guidance & Outlook

  • Maintains 2025 production guidance of 460‑500 k oz gold; expects to finish near the midpoint of that range.
  • Anticipates full‑year cash costs/AISC at or above the high ends of current guidance ($980‑$1,080 and $1,370‑$1,470 per oz respectively) because of higher Turkish royalty bands (max $5,101/oz) adding roughly $15/oz to cost guidance.

  • Royalty & Tax Updates

  • Effective July 24 2025, Turkish Mining Law amendments broadened the price‑linked sliding scale for state royalties; highest band now applies at $5,101/oz gold price (previously $2,101/oz).

  • Skouries Project – Term Facility & Derivatives

  • Drawdowns on Skouries Term Facility in Q2 2025: €154.1 M (year‑to‑date total).
  • Entered into zero‑cost gold collars covering 28,000 oz (put $3,000/oz, call $4,537/oz) settled monthly from July 2027 to Dec 2027.

  • Share Repurchase

  • Q2 repurchased & cancelled 2,167,400 shares at an average price of $20.57/share, total cost ≈$44.6 M.
  • Post‑period additional purchase: 680,953 shares at $20.29/share for $13.8 M.

  • Construction Milestones (Skouries)

  • Phase 2 construction ~70% complete; filtered tailings plant structural steel 51% finished (end Q2) → ~75% by end July.
  • Primary crusher building structure, conveyor foundations, and underground development progressing; underground access >200 m/month, 350‑m level reached.

  • Operational Highlights – Individual Mines

  • Kisladag: 46,058 oz produced (4 Mth ounce poured milestone).
  • Lamaque: 50,640 oz produced; higher throughput from Ormaque bulk sample processing.
  • Efemcukuru & Olympias: production declines offset by higher gold price; cost per oz increased accordingly.

  • Conference Call – Scheduled for August 1 2025, 11:30 AM ET (webcast link provided).

Notable Quotes

“Our second quarter results reflect strong operational execution,” said George Burns, President & CEO. “Disciplined capital and cost management…generated free cash flow of $61.5 M from our operating portfolio, excluding Skouries.”


Read the original news release →

More from Eldorado Gold Corporation