CERT 2.28 −2.6% FMAN 0.365 −8.8% AAUC 29.22 −5.8% WEC 0.015 +0.0% ATY 0.260 +0.0% GEN 0.060 +9.1% HMR 0.490 +2.1% SKP 0.165 +10.0% AZM 0.620 +0.0% AEM 259.53 −0.8% CG 29.58 −2.7% KS 0.160 +0.0% EMN 0.100 +5.3% CPAU 0.140 +0.0% SAG 1.23 +0.0% NAU 1.62 −9.0% CERT 2.28 −2.6% FMAN 0.365 −8.8% AAUC 29.22 −5.8% WEC 0.015 +0.0% ATY 0.260 +0.0% GEN 0.060 +9.1% HMR 0.490 +2.1% SKP 0.165 +10.0% AZM 0.620 +0.0% AEM 259.53 −0.8% CG 29.58 −2.7% KS 0.160 +0.0% EMN 0.100 +5.3% CPAU 0.140 +0.0% SAG 1.23 +0.0% NAU 1.62 −9.0%
Financings

Abcourt Mines increases loan financing by $2M (U.S.)

ABI · Price

Executive Summary

  • Abcourt Mines Inc. upsized its loan with Nebari Natural Resources Credit Fund II LP by an additional US$2 million, bringing total borrowings to US$10 million.
  • The proceeds will be used to accelerate development of the Sleeping Giant mine, including adding a third underground diamond drill and advancing Phase 2 at the sleep camp.
  • Concurrently, Abcourt issued 14,905,298 non‑transferable warrants to Nebari (exercise price C$0.093 per share, expiring July 3 2028, with reduction provisions if principal is prepaid).

Key Details

  • Original Loan: US$8 million tranche funded on July 3 2025.
  • Upsized Tranche 2: Additional US$2 million provided on the date of this release.
  • Total Borrowed Amount: US$10 million across two tranches.
  • Use of Proceeds: Accelerate Sleeping Giant mine development – add third underground diamond drill, expand mineral resources, and speed up Phase 2 at the sleep camp.
  • Warrant Issuance: 14,905,298 non‑transferable warrants issued to Nebari; exercise price C$0.093 per share; expiry July 3 2028; term may be reduced if principal prepaid before July 3 2026 (new term = later of July 6 2026 or 30 days after repayment).
  • Regulatory Conditions: Upsized loan and warrants subject to TSX‑V approval; warrants subject to a statutory hold period of four months and one day.

Notable Quotes

  • “The partnership with Nebari is great… increasing the number of workers sleeping on site will reduce transportation and offsite lodging cost, as well as accelerating development underground.” – Pascal Hamelin, President & CEO, Abcourt Mines Inc.
  • “Nebari is pleased to upsize our loan to Abcourt in support of advancing the development of its Sleeping Giant mine… positioned to achieve ramp‑up objectives in a favourable gold price environment.” – Steven Bowles, Managing Director, Nebari Natural Resources Credit Fund II LP.
Read the original news release →