S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Financings

Troilus Wins "Entrepreneur of the Year" Award From the Quebec Mineral Exploration Association, Recognizing Leadership in Advancing One of Canada's Largest Copper-Gold Projects

TLG · Price

Executive Summary

  • Troilus Gold Corp. was named “Entrepreneur of the Year” by the Québec Mineral Exploration Association, highlighting its progress on the Troilus copper‑gold project.
  • The company reiterated major milestones achieved since its May 2024 Feasibility Study, including $1.3 bn of ECA letters of interest, a mandated US$700 m debt financing syndicate, and indicative off‑take agreements with Aurubis AG and Boliden AB.
  • Engineering is >85% complete, permitting (ESIA filing) is finished, and the project is on track for a 2026 construction decision, positioning it as a significant future producer in Québec.

Key Details

  • Award Recognition: “Entrepreneur of the Year” by QMEA at Xplor 2025 gala in Montréal.
  • Resource Growth: Mineral resource base increased >500% since 2018; Feasibility Study (May 2024) projects a 50,000‑t/d operation with 22‑year mine life and ~303,000 oz Au‑eq per year (≈135.4 M lb Cu‑eq).
  • Project Financing:
  • US$1.3 bn in letters of interest from global Export Credit Agencies (press release 21 Nov 2024).
  • Mandated US$700 m senior debt financing led by an international lender syndicate, supported by European ECAs (press release 13 Mar 2025).
  • Off‑take Agreements: Indicative long‑term contracts with Aurubis AG and Boliden AB (press releases 10 Jul 2025 & 26 Aug 2025).
  • Permitting: ESIA filed June 2025 with Québec and federal regulators, concluding five years of studies and community consultation.
  • Engineering Progress: Basic engineering >85% complete, led by BBA Inc., on schedule to transition to detailed execution for a 2026 construction decision (press release 15 Oct 2025).
  • Economic Impact Estimates: At current metal prices, projected C$6 bn in Québec tax revenue and C$2.4 bn for Canada over mine life; >1,000 jobs during construction and >680 permanent operational jobs.

Notable Quotes

“We are deeply honoured to receive this recognition from the QMEA… Over the past year, we’ve delivered on every major front — from completing our Feasibility Study to filing our ESIA, securing international financing support, and advancing engineering toward construction readiness.” – Justin Reid, CEO & Director

“Troilus stands as an example of entrepreneurship within Québec’s mining industry… strengthens both Québec’s economic vitality and its credibility in international markets.” – Alain Poirier, General Manager, AEMQ

Read the original news release →