HDRO 1.51 +4.1% LOD 0.405 +1.2% GRZ 6.50 +0.0% ELBM 0.800 −1.2% AG 27.42 +2.5% PAAS 67.00 +1.8% GGM 0.035 +0.0% NTH 0.152 −4.7% SRC 1.76 −0.6% SAGE 0.150 +0.0% NIM 0.760 +4.1% LUCA 0.980 +2.1% SVM 16.64 −0.2% SRL 0.395 −3.7% CNL 20.51 +0.1% ARIS 25.12 +1.2% HDRO 1.51 +4.1% LOD 0.405 +1.2% GRZ 6.50 +0.0% ELBM 0.800 −1.2% AG 27.42 +2.5% PAAS 67.00 +1.8% GGM 0.035 +0.0% NTH 0.152 −4.7% SRC 1.76 −0.6% SAGE 0.150 +0.0% NIM 0.760 +4.1% LUCA 0.980 +2.1% SVM 16.64 −0.2% SRL 0.395 −3.7% CNL 20.51 +0.1% ARIS 25.12 +1.2%
Financings

South Star Provides Updates on Changes to Management and Board and Provides Operational Update

STS · Price

Executive Summary

  • Tiago Cunha appointed Interim CEO, President and Director; subscribes for C$2.085 M of convertible notes.
  • New CFO/Corporate Secretary Darren Prins hired; General Manager Rogerio Barcellos assigned to Santa Cruz graphite project.
  • Operational performance at Santa Cruz improves: second 20‑tonne container shipped in 1.5 months with product mix moving toward design specs; identified ~40 % operating cost savings and re‑evaluation of contractor agreements.

Key Details

  • Interim CEO Appointment: Tiago Cunha, largest shareholder, to subscribe for C$2.085 M (US$1.5 M) convertible notes into units of the Company.
  • CFO Appointment: Darren Prins joins as Chief Financial Officer and Corporate Secretary; brings 20+ years of finance, treasury, M&A experience.
  • General Manager Appointment: Rogerio Barcellos effective July 11 2025; tasked with debottlenecking Santa Cruz plant and expanding capacity to 10,000 t/yr graphite concentrate.
  • Director Resignation: Roger Mortimer resigned on August 20 2025.
  • Production Update – First Shipment (May 7 2025): ~20 t of graphite concentrate produced over eight months; product mix 75 % fines / 25 % flakes (design: 33 % fines / 66 % flakes).
  • Production Update – Second Shipment: Same 20 t produced in 1.5 months; product mix improved to 25 % fines / 75 % flakes, aligning closer to design specifications.
  • Cost‑Saving Review: Potential ~40 % operating cost reduction identified through permanent (energy efficiency) and temporary measures during next six months of ramp‑up.
  • Contractor Agreements: All contractor agreements under re‑evaluation to further reduce cash costs during plant debottlenecking.
  • Strategic Partnerships: Company actively evaluating partnerships to strengthen cash position, market presence, and accelerate capital execution.
  • Financing Outlook: Proceeds from private placements (announced Sep 30 2025) and the Sprott Bridge Loan Facility (announced Aug 26 2025) expected to fund achievement of 5,000 t/yr design capacity in 2026.

Notable Quotes

  • “The appointment of Tiago Cunha as Interim CEO brings seasoned capital‑markets expertise at a critical time for South Star,” – Marc Leduc, Chairman of the Board.
  • “Our operational improvements and cost‑saving initiatives demonstrate that we are on track to meet our design capacity targets and deliver value to shareholders,” – Darren Prins, CFO.